Section 5

Table 5-1 Parts Assembly Item Identification 

Item#

1

TUBE HOUSING ASSEMBLY

2

COUPLING NUT HOUSING

3

IN/OUTLET TUBE-FITTING INSERT

4

O-RING INSERT TO TUBE

5

O-RING INSERT TO FITTING

6

INLET END FITTINGS      

7

OUTLET END FITTINGS      

8

SEAL SPINDLE (SZ 2-6)

9

O-RING FOR SEAL SPINDLE (SZ 2-6)

10

GLASS METERING TUBE

11

FLOAT

12

INLET FLOAT STOP

13

OUTLET FLOAT STOP

14

TUBE SEAT GASKET/PACKING

15

CENTERING RING TUBE GASKET (SZ 2-6)

16

SLEEVE

17

LABEL CLEAR SCALE

18

RESERVED FOR LABEL WHITE BACKING

20

CENTERING RING

21

SCREW CENTERING RING

22

WINDOW ASSEMBLY

23

SCREW WINDOW

24

SIDE STRIP W/O ALARM (SZ 7-10)

25

RETAINER SIDE STRIP W/O ALARM (SZ 7-10)

26

SCREW SIDE STRIP W/O ALARM (SZ 7-10)

27

SCREW DRAIN HOLES (TOP ONLY)

30

ALARM SWITCH ASSY

33

CATRIDGE II VALVE / VALVE SPINDLE

34

ROLL PIN FOR VALVE

35

VALVE BUSHING (SZ 2-6)

36

O-RING TOP BUSHING (SZ 2-6)

37

O-RING OUTSIDE BUSHING (SZ 2-6)

38

LABEL SET

40

FLANGE PROTECTORS / END CAPS 

        24

25

Summary of Contents for GT1600

Page 1: ...Installation and Operation Manual X VA GT1600 eng Part Number 541B220AAG April 2020 GT1600 Series Brooks GT1600 Industrial Glass Tube Variable Area Flowmeter GT1600 Series...

Page 2: ...r electrical and pressure sources Operation 1 Slowly initiate flow into the system Open process valves slowly to avoid flow surges 2 Check for leaks around the flow meter inlet and outlet connections...

Page 3: ...n manual Failure to comply could result in serious personal injury or property damage Protective sleeve must remain over glass tube Meter sizes 7 10 only Fasten meter windows securely Failure to compl...

Page 4: ...lation General 17 Receipt of Equipment 17 Recommended Storage Practice 17 Return Shipment 17 Transit Precautions 18 Installation 18 Section 3 Operation Pre Operational Check 19 Operating Instructions...

Page 5: ...ches for GT1600 Sizes 2 6 15 1 7 Dimensions and Specifications Intrinsically Safe Switch Isolators 16 2 1 Typical Flowmeter Piping Configuration 18 3 1 Typical Flowmeter Piping Configuration 20s 5 1 G...

Page 6: ...peration The operating parts of the flowmeter consist of a tapered glass tube and a float which operates within the tube The fluid enters the bottom of the tube which has the smallest inside diameter...

Page 7: ...ting in the center of the tube The guide ribs do not follow the taper of the tube They are parallel to the tube centerline so that the proper operating clearance for the float is maintained for its en...

Page 8: ...ure Ratings Float wetted Materials of construction Maximum Operating Pressure PSIG bar at Max Operating Temperature Tube size Threaded process connections Flanged process connections Horizontal IN OUT...

Page 9: ...S 23 A 0 66 150 2 7 4 6 8 XV 8 A 0 99 220 4 6 9 8 XV 14 A 1 3 310 5 3 9 1 8 XV 31 A 1 7 400 11 20 9 XS 33 A 3 0 690 12 21 9 XV 87 A 3 6 830 26 44 9 XS 87 A 4 5 1000 32 55 10 XV64 A 6 1300 24 41 10 XS...

Page 10: ...Section 1 Figure 1 4 Dimensions GT1600 Series See Dimensions Tables on following pages 5...

Page 11: ...N H OUT 9 1 4 0 72 120 0 V IN V OUT 1024 19 69 500 0 H IN V OUT 7 8 3 94 100 0 H IN V OUT 9 1 4 0 72 120 0 V IN H OUT 7 3 8 94 100 0 V IN H OUT 9 10 4 72 120 0 H IN H OUT 7 22 88 8 3 50 88 9 H IN H OU...

Page 12: ...H OUT 9 10 15 00 381 0 4 00 101 6 H IN H OUT 9 02 229 1 0 83 21 0 V IN V OUT 11 20 284 6 H IN V OUT 10 11 256 9 0 83 21 0 V IN H OUT 10 11 256 9 0 83 21 0 V IN V OUT Retro t only 4 GT1305 1305 7 75 1...

Page 13: ...v 1 Groups A thru G Ex mb IIC T6 Gb Ex mb IIIC T85 C Db Standard Version KIWA 18ATEX0013 X IECEx KIWA 18 0008X Declarations Mark Meter Options Standards Directives Marking Status Certificate Explosion...

Page 14: ...ipment depends not on the equipment itself but on operating conditions of the process uid gas owing through the equipment The equipment by itself does not generate heat Due to this reason the temperat...

Page 15: ...nsists of a biasing magnet and hermetically sealed reed switch which is insulated to prevent damage from mild shock and normal pipe vibration The contact rating of the switch is very low 0 5A An exter...

Page 16: ...t have a breaking capacity in accordance with the prospective short circuit current of the circuit to properly break the systems highest short circuit current In case device is mounted in an area wher...

Page 17: ...ically safe circuits An additional external connection facility for an equipotential bonding conductor is provided on the metallic enclosure The product should be installed by suitably trained personn...

Page 18: ...Section 1 13 Figure 1 5 Reed Switch Alarm UL Installation...

Page 19: ...tacts may be made to operate simultaneously For hazardous area applications Brooks can supply an approved Namur power supply amplifier relay unit to obtain an intrinsic safe current circuit Please ref...

Page 20: ...type of valve can cause pressure shocks which can damage the glass tube GT1600 Alarm Contact Bistabble Inductive Switches Meter Size 2 to 6 Application Electrical Equipment for use in Hazardous locat...

Page 21: ...Section 1 Figure 1 7 Dimensions and Specs Intrinsically Safe Switch Isolators 16...

Page 22: ...ged or missing parts Recommended Storage Practice If intermediate or long term storage of equipment is required it is recommended that the equipment be stored in accordance with the following a Within...

Page 23: ...recommended that the typical piping arrangement shown in Figure 2 1 be used when installing the meter This piping arrangement permits the meter to be isolated from the flow for servicing or cleaning...

Page 24: ...eference lines are not aligned loosen the screws securing the scale and move it until the marks are in alignment Then tighten the screws Operating Instructions After the flowmeter has been properly in...

Page 25: ...H IN V OUT 9 1 1 0 7 38 441 3 V IN H OUT 7 1 8 6 75 425 5 V IN H OUT 9 10 17 38 441 3 V IN V OUT Retro t only 4 GT1307 1307 16 94 430 2 H IN H OUT 7 8 3 94 100 0 H IN H OUT 9 1 4 0 72 120 0 V IN V OUT...

Page 26: ...Section 4 Overview 21...

Page 27: ...e float stops float and end fittings with a suitable solvent 6 Install the inlet float stop into the metering tube Refer to Figure 1 3 for the correct orientation of the float Slide the float into the...

Page 28: ...Section 5 General See Figures 5 1 and 5 2 and Table 5 1 for parts assembly drawings and parts list Figure 5 1 GT1600 Sizes 2 6 Parts Assembly Drawing Ref GT16XX001_1 23...

Page 29: ...Section 5 Figure 5 2 GT1600 Sizes 7 10 Parts Assembly Drawing Ref GT16XX002_1 24...

Page 30: ...14 TUBE SEAT GASKET PACKING 15 CENTERING RING TUBE GASKET SZ 2 6 16 SLEEVE 17 LABEL CLEAR SCALE 18 RESERVED FOR LABEL WHITE BACKING 20 CENTERING RING 21 SCREW CENTERING RING 22 WINDOW ASSEMBLY 23 SCR...

Page 31: ...n nearest to you START UP SERVICE AND IN SITU CALIBRATION Brooks Instrument can provide start up service prior to operation when required For some process applications where ISO 9001 Quality Certifica...