COMMISSIONING
The fire alarm installer shall ensure that all documentation, logbook, handbook
(operators and installers manuals), as-installed drawings, and check list are
available at the time of commissioning.
The fire alarm system installer shall rectify any faults in the fire detection and alarm
installation, as appropriate, where the results of the commissioning tests are outside
the manufacturer's limits.
6.1
As-Installed Diagrams and Installer's Statement
An as-installed diagram of the wiring layout of the complete installation, including the
positions of the Smoke/Heat Alarms and any ancillary devices, should be provided
before a final inspection is made.
6.2
Commissioning Tests
6.2.1
System Configuration
Step 1
Ensure that the control panel and smoke/heat alarm locations are
appropriate for the type of site and usage.
Step 2
Check that all smoke / heat alarms used in the system are:
Listed in this manual
Compatible with the installed zone circuit, particularly that the
permitted number of smoke/heat alarms for the zone is not
exceeded; and
Installed in an environment for which they are suitable
Check for any sign of contamination due to installation or other
building works.
Step 3
Check that all ancillary control functions for the system are:
listed in this manual
wired as per design specification.
Step 4
Check that the AC mains power supply for the system has been
provided in accordance with AS3000.
Step 5
Visually check all field wiring terminations (refer to the block wiring
diagram shown in figure 6 of this manual).
Step 6
Ensure the End of Line Device is in correct location (last device or alarm
in the zone), visually confirm wiring is correct (refer to figure 6).
Step 7
Check that the battery is fitted. It should be of a suitable type and
capacity.
Step 8
Check that as-installed drawings have been correctly marked up and
that they are consistent with the installation.
Step 9
Record the results of the commissioning test on the commissioning
sheet in this Handbook.