Section 3 Operation
Section 3 Operation
23
Operating Procedure
After the flowmeter has been properly installed in the process, it is ready
for operation. When initiating flow, slowly open the valve to avoid a flow
surge.Bypass is a help in bringing the flow on smoothly. Avoid starting a
pump to supply the flowmeter without the use of a valve upstream of the
flowmeter.
Operation of Inductive Alarm
A. Start-up the meter as described in Section 3-1
B. To modify the alarm set points, remove the side cover of the indicator
housing by removing the four screws.
C. Set the alarm position by loosening the screw mounting the switch to
the plate.
D. Hold the pointer to the desired alarm flow rate.
E. Move switch assembly until the metal initiator, attached to the pointer,
is not inserted into the switch.
F. Tighten the screw mounting the switch to the plate.
G. Replace the indicator housing cover and gasket and secure with the
four screws.
Operation of Transmitter
A. Start-up meter as described in Section 3-1.
B. Programming is performed prior to shipment. The transmitter is
preprogrammed prior to shipment for the following parameters based
on the order information, meter configuration and application.
If
parameters are not specified in the customer purchase order, the
defaults inherent to the electronics will be as shown in (parenthesis).
Pre-Programmed Parameters
Serial Number
Flow Rate units of measure (gpm)
Low Flow cutoff (5% FS flow)
Analog Output LoRange
(4 mA @ 0% flow)
Analog Output HiRange
(20 mA @ 100% flow)
Brooks
®
Ar-Mite
TM
MT3750C
Summary of Contents for Ar-Mite MT3750
Page 19: ...Section 2 Installation 15 Figure 2 3 Inductive Switch Wiring Brooks Ar MiteTM MT3750C...
Page 26: ...Section 2 Installation Brooks Ar MiteTM MT3750C 22 Figure 2 9 Transmitter Wiring Diagram...
Page 30: ...Section 3 Operation Brooks Ar MiteTM MT3750C 26 Figure 3 1 Reed Switch Alarm...
Page 34: ...Section 5 Parts List 30 Figure 5 1 Model MT3750 Exploded View Brooks Ar MiteTM MT3750C...