RESET
The flow charts show a complete listing of parameters. For
actual application the number of available parameters is
dependent on the setup conditions, and should be less than
that shown in the flow charts.
Press key for 4 seconds to enable up/down key
function, and the LOCK indicator will be extinguished.
Note 1.
Note 2.
1-6 Limit Control Operation
HIGH LIMIT OPERATION
If Hi. is selected for OUT1, the unit will perform high limit control.
When power is applied the OUT1 relay is de-energized. After 6.5
seconds self-test period, if the process is below the high limit set
point (HSP1), the output 1 relay will be energized and OP1 indicator
will go off. If the process goes above the high limit set point, the
relay will be de-energized, the OP1 indicator will go on and the
display will show the process value. After the process falls below the
high limit set point and the RESET key is pressed or the remote
reset input is applied, the relay will be energized and the OP1
indicator will go off.
HSP1
ON
OFF
OUT1 Relay
A, B ,C=Reset is applied
O1.HY= Output1 hysteresis
Figure 1-4 High Limit Operation
PV
A
B
C
13
HSP1 O1.HY
UM0L911C