12
4.3 Control box
The control box is equipped with all control elements and instruments for monitoring and controlling the
machine.
1.
Warning lights
2.
Hour counter
3.
Rotating valves On/Off
4.
Fan-unit On/Off
5.
Compressor On/Off
6.
Emergency STOP
7.
Connection for the dusthose to
the blast machine
8.
Connection for the power
supply cable of the fan unit.
5. Operation
5.1 Starting / stopping the machine
Connect the fan-unit and filter-unit with the airhose and supply cable (8.)
Connect the dust hoses to the blastmachine and dust collector (7.)
Connect the dust collector to the power supply
Check the warning lights, if a warning light is lit, see 5.4 Startup Problems for guidance.
Switch on the compressor motor (5.)
Switch on the fan motor (4.) wait for the fan to get at full speed.
Switch on the rotating valve motor (3.)
Carry out this actions in opposite sequence to stop the machine.
5.2 Work with the machine
Be sure that rotating valve motor is switched on and the compressor pulses at the correct pressure.
This will increase the life-time of the filter cartridges.
Regularly check the contents of the big bag, exchanging the big bag too late can cause a big mess and
be potential dangerous to the health.
Regularly use the air pistol to remove water from the air tank.
Excessive water can have a negative impact on the pulse power and shortens the life-time of the filter
cartridges.
The suction power of the dust collector can be adjusted with the air flow pressure regulator on the
silencer. Slide the hood open for more power, and close it for less power. (Page 5, point 3)