3. Installation Instructions
A. Workplace Reguirements
(1) Location: Indoor only. Any outdoor area where the equipment is to be located
should meet all the environmental requirements.
(2) Operating environment: 10
~40
(50
~ 104
), 30%~80% RH
(3) Power supply: 100 - 240V~, 50/60Hz
B. Unpacking and Assembling
(1) Put down the packaging box on where the equipment will be located with the
written instructions on top. Open up the top and take out the accessory bag.
(2) Remove hinge pads in the corners and put up the upper part of the
equipment.
(3) Remove the loadcell pad and the cover of the equipment.
(4) Remove the elastic band that pulls the hand electrode cables together and
then the holder for hand electrode.
(5) Lift up the back of the lower part of the equipment gently to remove the
support pads at the back.
(6) Before taking out the equipment, tighten up the screws connecting the upper
and lower part with a box wrench. The box wrench is attached to a tape
underneath the hinge cover.
(7) Hold the bottom of upper part and the center of lower part on both sides with
hands and take the equipment out of the box. Take the equipment to where it
will be installed.
(8) Tighten up the four screws connecting the upper and lower part with the box
wrench.
(9) Adjust the height of equipment using the four legs attached to the lower part
of the equipment and one leg from the upper part of the equipment. Keep the
equipment level, using the level indicator located at the center of the
connection unit.
<Raise up>
<Raise down>
Summary of Contents for InBody 720
Page 1: ...User s Manual...
Page 44: ...1 Setup Menu 2 Quick Setup 3 DATABASE 4 Modification Example Chapter 3 Setup Establishment...
Page 59: ...1 Consumables 2 Basic Equipment 3 Options Chapter 5 Consumables...