Step 16 Install Roof Sheathing
1.
Install roof sheathing per layout below. Make sure the gables and trusses are plumb. Working
from back to front start first row of at the 49" mark and flush with rear gable siding. Insure
sheathing meets the center of the truss at the break. Use 7d sinkers spaced 12" apart. The top
row of roof sheathing will be about 1" below the ridge to allow for ventilation.
Important: Make sure the front gable is plumb and the roof sheathing extends 9" past the
siding along the face of the gable.