 6. Remove and save the short 2x4 blocks. They

will be used in a later step.

Detail 'B'

!

!

Step 9

Assemble Roof Trusses

1.

Place (2) two 80-1/2" long 2x4 truss rafters and a 82" long collar tie together as shown below.

The collar tie has an angle cut on both ends.  Reposition the lower 2x4 blocks to hold the truss
rafter and collar tie in place. See 'Detail B'.

2.

Secure the 2x4 truss rafters at the top with a 8" x 20" wood gusset. Apply wood glue between

the 2x4s and the gusset. Nail the gusset to the 2x4s with (14) fourteen 6d common nails.

3.

Install (2) two 12"x24" gussets at ends of the collar tie. Glue and nail using 14 nails per gusset.

4.

Turn this truss over and apply wood gussets to the opposite side.

5.

Repeat to assemble (4) four more trusses if you are building a 12' long building.

2x4 Block

Top Gusset

12"x24" Gusset

2x4-82" Collar Tie

!

Install collar tie the same
distance from edge of floor.

80-1/2" Truss Rafter

2x4 Block

2x4 Block

2x4 Block

80-1/2" Truss Rafter

Summary of Contents for Fairview-R

Page 1: ...ted Under the copyright laws this manual may not be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2018 Fairview R Building Size 12 x12 205 Arlington Drive Gre...

Page 2: ...y from the side walls The material that is included in our kit is listed on the back page The optional floor package if purchased will be supplied by a local lumber supplier Our kit does not include t...

Page 3: ...oor joist to 11 9 Treated lumber may be thicker than 1 1 2 Take this into account when cutting the length of floor joists Shorten joist measurements if necessary to obtain 12 0 building width 1 Cut 2...

Page 4: ...Install the first siding panel with the LAP edge flush the end of the wall and extending 3 4 below the bottom plate Use 8d galv nails spaced 8 apart 5 Install 2 two more siding panels Siding Extends...

Page 5: ...tend 3 4 below the bottom plate Nail both siding panels to frame 1 Locate 2 two 34 3 4 long 2x4s and position them together Indicate with X marks where studs will be located 2 Install 3 three 72 wall...

Page 6: ...elow the bottom plate 5 Install 2 two more siding panels Cut the last panel to extend 3 1 2 beyond the wall frame X X X X X X 68 1 2 Wall Plate 2x4 72 Wall Studs Step 3 Assemble 12 Long Sidewalls No D...

Page 7: ...ndow box Step 4 Assemble 2 Two Front Wall Frames 1 Cut 2 two 58 1 2 long 2x4s to 56 1 4 Position them together and indicate with X marks where studs will be located 56 1 4 Wall Plate 56 1 4 Wall Plate...

Page 8: ...eader Support Step 6 Apply Siding to Right Front Wall Frame OSB Filler 1 Gather 2 two 31 1 2 long 2x4 boards and 3 1 4 x 31 1 4 OSB filler panel Nail header together from both sides with 10d sinkers s...

Page 9: ...blocks to the floor using 2 1 2 screws This will ensure that the gable frames and the trusses assembled next are identical 4 Secure the top of the truss rafters together with a 1 x4 barbed metal driv...

Page 10: ...rs at the top with a 8 x 20 wood gusset Apply wood glue between the 2x4s and the gusset Nail the gusset to the 2x4s with 14 fourteen 6d common nails 3 Install 2 two 12 x24 gussets at ends of the colla...

Page 11: ...sidewall panels Nail through the wall stud into the ends of the header Toenail into the top wall plates 4 Install the 31 1 2 door header between the front wall panels 5 Remove the center 2 two 2x4 84...

Page 12: ...Door Trim 1 Install 2 two 75 3 4 long 1x3 corner trim boards to the side wall flush with the top 2x4 wall plate and flush with siding on the front and back walls Use 8d galv nails spaced 12 apart 2 R...

Page 13: ...5 Repeat to install filler on the opposite wall 1x4 Trim Step 13 Install Front and Back Wall Trim 1 Install 2 two 75 3 4 long 1x4 trim boards on the front wall flush with top of 2x4 wall plate and flu...

Page 14: ...le over so bottom plate is on edge on floor Support gable studs and rafters with 2 two 2x4 72 boards stacked This will give you a solid surface when nailing siding 2 Install left gable siding panel wi...

Page 15: ...2 Install metal hangers to the tie plate with 6d common nails The opening should line up with the X mark the bottom of the opening flush with the 2x4 tie plate Detail D 24 20 5 8 Measure from Backsid...

Page 16: ...sh with the gable siding Use 6d galv nails Siding Filler 2x4 Blocks 1 Set roof trusses Secure trusses to metal hangers with 6d common nails 2 Install short 2x4 blocks at both ends of each truss Secure...

Page 17: ...Edge 2x4 Tie Plate 2x4 Soffit Block 1 Starting at the rear of the building install a 1x4 6 white pine fascia board against the rear gable trim Install the fascia so the bottom edge of the roof sheathi...

Page 18: ...sinkers spaced 12 apart The top row of roof sheathing will be about 1 below the ridge to allow for optional ventilation Important Make sure the front gable is plumb and the roof sheathing extends 7 pa...

Page 19: ...lv nails Cut next panel to fit Repeat on other side 3 Starting at the peak install 2 two 42 3 8 long 2x3s between the roof sheathing and the 7 soffit panels Use 6d galv nails on soffit and 7d sinkers...

Page 20: ...back side of the door When doors are closed this 2x4 will be in the center where doors meet Lay the door with the trim facing up and install 3 three 5 hinges to the right side To position the hinge p...

Page 21: ...u can move the trim in or out to make the door spacing equal 2 Determine position of hinges and install to side trim with 2 screws 4 Install a barrel bolt on the lower back of the left door to secure...

Page 22: ...l ventilation Step 28 Install Roofing Not Supplied in Kit 1 Install metal roof edging on the perimeter of the roof area If you are not installing shingles at this time you can purchase felt paper to p...

Page 23: ...1x4 Wall Trim 72 3 ea 1x3 Door Trim 72 2 ea Pre built Door 32 x 71 1 2 5 Collar Ties 2x4 82 14 Truss Rafters 2x4 80 1 2 48 Wall Studs 2x4 72 4 Wall Plates 2x4 68 1 2 2 Wall Plates 2x4 67 1 2 2 Wall P...

Reviews: