2
Foundations
2.1
Foundation construction
A foundation plan is supplied to assist with constructing the foundations. All given measurements for the
foundation MUST be observed. The central mast climbing structure is constructed according to the valid
foundation plan.
The minimum concrete quality to be used is C20/25.
The following work steps must be carried out for foundation construction:
1.
Approximately determine the foundation points on site.
2.
Excavation of the pit for the foundations according to the specifications from the foundation
plan.
3.
Concrete foundation using concrete with the minimum quality C20/25.
4.
Allow the concrete to completely hydrate (min. 2 weeks)
5.
Create a surface for the subsequent installation of the central foundation slab and the outer
end points.
6.
Position the foundation slab on the central foundation. Mark bores for the outer foundation
points and the central foundation slab and mount the connection anchor according to step
2.2.
7.
Attention:
The foundation slab of the central foundation is installed with an M16 connection
anchor and the outer foundation points with M20 connection anchors.