XPR-10 Series Two-Post Lifts
21
P/N 5900951 — Rev. D — May 2019
Putting Equalizing Cables into Position
It is much easier to put the Equalizing Cables into position
before
you stand up the Posts. Note that
this is
not a full install
of the Equalizing Cables, just putting them into position.
⚠
CAUTION
BendPak recommends wearing gloves while handling the Equalizing Cables.
The Equalizing Cables keep the Lift Heads synchronized. You do not want one Lift Head lowering or
raising faster than the other Lift Head; the Vehicle on the Lift would become unstable and could fall.
The following drawing shows an Equalizing Cable; the ends are exaggerated for clarity.
Important
: For Symmetric models, the two Equalizing Cables are the same length.
For
Asymmetric models, the two Equalizing Cables are different lengths
. For
Asymmetric models, the longer cable is routed over the Overhead Assembly Sheaves
on the Approach side of the Lift (the Overhead Assembly Sheaves that are furthest
apart from each other).
Not necessarily to scale. Not all components shown. Some components exaggerated for clarity.
Asymmetric model shown, so one cable is longer than the other.
Summary of Contents for XPR-10 Series
Page 9: ...XPR 10 Series Two Post Lifts 9 P N 5900951 Rev D May 2019 Specifications ...
Page 77: ...XPR 10 Series Two Post Lifts 77 P N 5900951 Rev D May 2019 Labels ...
Page 78: ...XPR 10 Series Two Post Lifts 78 P N 5900951 Rev D May 2019 ...
Page 79: ...XPR 10 Series Two Post Lifts 79 P N 5900951 Rev D May 2019 ...
Page 81: ...XPR 10 Series Two Post Lifts 81 P N 5900951 Rev D May 2019 ...
Page 82: ...XPR 10 Series Two Post Lifts 82 P N 5900951 Rev D May 2019 ...
Page 83: ...XPR 10 Series Two Post Lifts 83 P N 5900951 Rev D May 2019 ...
Page 84: ...XPR 10 Series Two Post Lifts 84 P N 5900951 Rev D May 2019 ...
Page 85: ...XPR 10 Series Two Post Lifts 85 P N 5900951 Rev D May 2019 ...
Page 86: ...XPR 10 Series Two Post Lifts 86 P N 5900951 Rev D May 2019 ...
Page 87: ...XPR 10 Series Two Post Lifts 87 P N 5900951 Rev D May 2019 ...
Page 88: ...XPR 10 Series Two Post Lifts 88 P N 5900951 Rev D May 2019 ...
Page 91: ...XPR 10 Series Two Post Lifts 91 P N 5900951 Rev D May 2019 Maintenance Log ...