XPR-10 Series Two-Post Lifts
15
P/N 5900951 — Rev. D — May 2019
Installation
The installation process includes multiple steps. Perform them in the order listed.
Reviewing the Safety Rules
When installing a Lift, your safety depends on proper training and thoughtful operation.
⚠
WARNING
Do not install this equipment unless you have automotive lift installation training.
Always use proper lifting tools, such as a Forklift or Shop Crane, to raise heavy
components. Do not install this equipment without reading and understanding this
Manual and the Labels on the unit.
Only fully trained personnel should be involved in installing this equipment. Pay attention at all times.
Use appropriate tools and lifting equipment. Stay clear of moving parts.
⚠
WARNING
You must wear appropriate protective equipment at all times during installation:
leather gloves, steel-toed work boots, eye protection, back belts, and hearing
protection.
Preparing for Electrical Work
You will need to have a licensed, certified Electrician available at some point during the installation.
⚠
DANGER
All wiring
must
be performed by a licensed, certified Electrician.
Make sure all electrical work conforms to applicable local, state, and federal codes, rules, and
regulations, such as state and federal OSHA regulations and electrical codes.
Notify your Electrician in advance so they come prepared with the items required to connect to the
facility’s power system or an appropriate power cord with plug for connecting to an appropriate power
source, a Power Disconnect Switch, and a Thermal Disconnect Switch. These items are
not
supplied
with the Lift.
The Electrician needs to:
•
Connect to power
. The Power Unit comes with a pigtail for wiring to a power source. Have your
Electrician connect a power cord with plug to the electrical box on the Lift (for connection to a
power outlet) or have them wire it directly into the electrical system at the Lift location.
Note that
installing
the Power Unit and
connecting
the Power Unit to a power source are separate
procedures and are done at different times in the installation process. You do
not
need an
Electrician to
install
the Power Unit, but an Electrician is
required
to
connect
the Power Unit to
the power source.
•
Connect the Microswitch wiring to the Power Unit
. The Microswitch has to be wired to
the Power Unit. The necessary wiring is included with the Lift.
•
Install a Power Disconnect Switch
. A Power Disconnect Switch is used to shut down the
Lift in the event of an electrical circuit fault, emergency situation, or when the Lift is being serviced.
Refer to
Installing a Power Disconnect Switch
for more information.
•
Install a Thermal Disconnect Switch
. A Thermal Disconnect Switch automatically shuts
down the equipment in the event of an overload or an overheated motor. Refer to
Installing a
Thermal Disconnect Switch
for more information.
Summary of Contents for XPR-10 Series
Page 9: ...XPR 10 Series Two Post Lifts 9 P N 5900951 Rev D May 2019 Specifications ...
Page 77: ...XPR 10 Series Two Post Lifts 77 P N 5900951 Rev D May 2019 Labels ...
Page 78: ...XPR 10 Series Two Post Lifts 78 P N 5900951 Rev D May 2019 ...
Page 79: ...XPR 10 Series Two Post Lifts 79 P N 5900951 Rev D May 2019 ...
Page 81: ...XPR 10 Series Two Post Lifts 81 P N 5900951 Rev D May 2019 ...
Page 82: ...XPR 10 Series Two Post Lifts 82 P N 5900951 Rev D May 2019 ...
Page 83: ...XPR 10 Series Two Post Lifts 83 P N 5900951 Rev D May 2019 ...
Page 84: ...XPR 10 Series Two Post Lifts 84 P N 5900951 Rev D May 2019 ...
Page 85: ...XPR 10 Series Two Post Lifts 85 P N 5900951 Rev D May 2019 ...
Page 86: ...XPR 10 Series Two Post Lifts 86 P N 5900951 Rev D May 2019 ...
Page 87: ...XPR 10 Series Two Post Lifts 87 P N 5900951 Rev D May 2019 ...
Page 88: ...XPR 10 Series Two Post Lifts 88 P N 5900951 Rev D May 2019 ...
Page 91: ...XPR 10 Series Two Post Lifts 91 P N 5900951 Rev D May 2019 Maintenance Log ...