HD-14T Four Post Lift
33
P/N 5900037 — Rev. F — February 2022
The following procedure assumes you have the four Lifting Cables and Sheaves you removed prior to
installing the Runways.
To route Lifting Cables A and C
:
1.
Starting with Lifting Cable A
, remove the Nut and Washer from the Threaded End (but keep
it nearby, you will need it soon). Check the label to make sure you have the correct Lifting Cable.
2.
Route the Threaded End of Lifting Cable A into its Large Window on the Crosstube, push it
towards Post A, and then pull the Threaded End out of the Crosstube at the bottom of the Gusset.
3.
Route the Threaded End of Lifting Cable A under where the Gusset Sheave will go when it is
reinstalled, then route it up past the top of the Crosstube Gusset.
Important
: When routing a Lifting Cable in its Post, the Cable must go
under
the Gusset Sheave
and be on the side of the Slack Safety Sheave. When the Cables are pulled tight, the
Cable prevents the Slack Safety from engaging, which is what you want. If the Cable is
not in this exact location
, the Slack Safeties will
not
work correctly.
Summary of Contents for HD-14T
Page 7: ...HD 14T Four Post Lift 7 P N 5900037 Rev F February 2022 Components ...
Page 9: ...HD 14T Four Post Lift 9 P N 5900037 Rev F February 2022 Specifications ...
Page 67: ...HD 14T Four Post Lift 67 P N 5900037 Rev F February 2022 Wiring Diagrams ...
Page 68: ...HD 14T Four Post Lift 68 P N 5900037 Rev F February 2022 Labels ...
Page 69: ...HD 14T Four Post Lift 69 P N 5900037 Rev F February 2022 ...
Page 70: ...HD 14T Four Post Lift 70 P N 5900037 Rev F February 2022 ...
Page 71: ...HD 14T Four Post Lift 71 P N 5900037 Rev F February 2022 Parts Drawings ...
Page 72: ...HD 14T Four Post Lift 72 P N 5900037 Rev F February 2022 ...
Page 73: ...HD 14T Four Post Lift 73 P N 5900037 Rev F February 2022 ...
Page 75: ...HD 14T Four Post Lift 75 P N 5900037 Rev F February 2022 Maintenance Log ...