7.

 

Operation of the BusHead 

 

7.1.

 

Commissioning 

 
During commissioning it is recommended to leave the parameter 

Configuration Lock on FALSE (default setting). In this mode it 

is possible to find the optimal topology for the LioN-Link system and the most favorable wiring solution. After the final 
configuration has been determined this parameter should be set to TRUE to immediately detect permutations of I/O-modules or 

a wrong wiring and to check the desired topology.  

 

 

7.2.

 

Exchange of I/O-modules 

 

A defective module can be replaced by an equivalent one without interruption of the power supply. After exchange the I/O-
module is detected automatically and the bus communication is started again. 

 
In order to minimise the stock-keeping with replacement modules it possible also to replace the I/O-modules with only digital 

inputs  by a universal module without changes to the configuration. This means, the following I/O-modules in first row replace 
the ones in the second row. 

0942 UEM 650  ->  0942 UEM 651 
0942 UEM 600  ->  0942 UEM 601 

0942 UEM 700  ->  0942 UEM 701 

 
 

The power supply for the actuators on a universal module is not needed as far as the module is used as an input 
module only. 

In this case no diagnostics of the actuator power is indicated or evaluated! 

 

 

7.3.

 

Bus interruptions and restart  

 

During an interruption of the bus line of one or both LioN-Link lines the MS and NS indicators start flashing. A diagnostic 
message is sent to the master. This behaviour explains itself from the fact that in this case the current configuration of the 

DeviceNet system does no longer comply with the target configuration. Therefore the communication over the DeviceNet bus 
line is interrupted.  

 
The BusHead restarts cyclically and tries to find the lost modules again. During the restart process the MS and NS indicators as 

well as the green and red LioN-Link indicators of the interrupted line (IO S1/S2) flash in cyclic change. For the LioN-Link line 
being not concerned only the green indicator IO (IO S1/S2) flashes cyclically. 

 
The red and green IO indicators LED of all I/O-modules that are connected with the BusHead flash in cyclic change (restart 

process). The red IO indicator is active permanently on those I/O-modules that lost the connection. 

If both, the bus connection and voltage supply are interrupted no indicators are illuminated. 

 

As soon as the interruption in the LioN-Link is repaired, the system restarts independently. Also, the diagnostic message 

that was caused by the incorrect configuration, is reset in the DeviceNet system. 

 

 

The position of the interruption in the LioN-Link line can be recognised by the status of the indicators. 

 

 

Summary of Contents for Lumberg LioN-Link 0940 DSL 601

Page 1: ...Technical Manual 0940 DSL 601...

Page 2: ...ports M12 plug socket 5 pole A coded 12 5 1 2 Power supply connector for the BusHead M12 plug 5 pole 12 5 1 3 Link system connector M12 socket 5 pole 12 5 2 Intermediate power supply feed on LioN Link...

Page 3: ...olling 23 6 7 2 Change of State 23 7 Operation of the BusHead 24 7 1 Commissioning 24 7 2 Exchange of I O modules 24 7 3 Bus interruptions and restart 24 7 4 Diagnostics 25 7 5 System expansion 25 8 T...

Page 4: ...s please do not hesitate to contact us We will be glad to be at your disposal at any time Belden Deutschland GmbH Lumberg Automation Im Gewerbepark 2 58579 Schalksmuehle Germany Tel 49 0 23 55 5044 00...

Page 5: ...ferences in the residential area In this case the operator can be required to accomplish appropriate measures The proper and safe function of the product requires an appropriate transport storage inst...

Page 6: ...ce as well as their knowledge of the relevant standards have the same level of knowledge as after a technical education due to an activity in a comparable area for several years Modifications to the h...

Page 7: ...distance between two link participants is arbitrary The permissible overall length for each line may not be exceeded however Using the maximum expansion of the system an additional feed of the power s...

Page 8: ...d with M12 socket straight 5 pole A coded 0935 253 106 M Connecting cable for DeviceNet and LioN Link line single ended with M12 socket angled 5 pole A coded 0935 253 107 M Connecting cable for Device...

Page 9: ...ge without notice Version 1 0 June 2010 Page 9 of 27 T connectors 0906 UTP 101 T connector for daisy chaining the power supply Pay attention to the current load 0906 UTP 104 T connector for additional...

Page 10: ...Technical Manual LioN Link DeviceNet Subject to change without notice Version 1 0 June 2010 Page 10 of 27 4 Mounting 4 1 Outer dimensions...

Page 11: ...a flat washer according to DIN 125 has to be used Important note For the derivation of interference currents and or for the EMC stability the module provides a metal grounding sheet It is necessary t...

Page 12: ...5 pole Colour code of the connector orange Connector Pin Signal Function 1 Drain Shield 2 24 V Power supply 3 GND 0 V Power supply 4 CAN_H Data signal DeviceNet IN OUT 5 CAN_L Data signal Connector Pi...

Page 13: ...dules During the planning of a machine or a plant it has to be considered that starting from certain cable lengths an intermediate power supply feed for the electronics and sensors of the I O modules...

Page 14: ...nk line a calculation table as a Microsoft Excel sheet is available under http www beldensolutions com en Service Downloadcenter Software_Lumberg index phtml The table determines the voltage drop on t...

Page 15: ...s the address 63 is used automatically 6 2 Data rate The DeviceNet BusHead 0940 DSL 601 supports all data rates that are released by the ODVA These are 125 kBit s 250 kBit s and 500 kBit s The Bushead...

Page 16: ...tion Adapter 6 4 1 Configuration of the LioN Link system Click on the part description of the BusHead 0940DSL601 in the hardware list Move the system to the DeviceNet line The DeviceNet node address a...

Page 17: ...cording to their physical installation Start with the first module at line 1 next to the BusHead Then insert the subsequent I O Modules of line 1 followed by those of line 2 Observe the correct order...

Page 18: ...elect the button Edit I O Parameters or doubleclick on the device name of the LioN Link system in the scanlist to edit the I O parameters Select desired communication mode and the number of input and...

Page 19: ...1 0 June 2010 Page 19 of 27 6 5 Parameter settings Access to the parameter settings of the BusHead and the I O modules of the LioN Link system can be obtained by a doubleclick on the BusHead or the I...

Page 20: ...revision The firmware version of the BusHead can be read out with the configuration tool Access is obtained using the class 102 instance 01 and the attribute 03 3 Count of modules line 1 This paramete...

Page 21: ...ts operation only if the actual and stored configuration are identical Access is obtained using the class 102 instance 01 and the attribute 07 8 Reset Module Configuration This parameter is editable i...

Page 22: ...nt Process data The process data are divided into consumer output data and producer input data The process data are transferred as a block according to the DeviceNet specification 6 6 1 Process data o...

Page 23: ...an incorrect status 0 I O module with number 1 16 is configured correctly Please consider that only the first detected configuration error can be reported 6 6 2 Process data of the I O modules The pro...

Page 24: ...module only In this case no diagnostics of the actuator power is indicated or evaluated 7 3 Bus interruptions and restart During an interruption of the bus line of one or both LioN Link lines the MS...

Page 25: ...bytes of an I O module can be obtained by the class 101 The instance is built up according to the respective position of the I O module on the LioN Link line starting with the first I O module in LioN...

Page 26: ...e power supply for the fieldbus interface Rated voltage US 24 V DC Voltage range 11 30 V DC Current consumption typ 10 mA Reverse polarity protection yes Operation indicator US LED green Connection vi...

Page 27: ...dules permuted red green alternating flashing Restart of line 1 and or line 2 S1 S2 off Line 1 and or line 2 not used no I O module connected green Ethernet connection to another participant exists ye...

Reviews: