Commissioning
EL47xx
157
Version: 2.7
Fig. 196: Process Data tab, adaptation of process data in SM1
Select SM0, then SM1 (Fig.
Process data tab, adjusting the process data in SM0 and SM1
), and in the field
below (PDO assignment) select the number of process data corresponding to the oversampling factor, in this
example 80
dec
.
In the PDO list on the right compare the PDO index with the last PDO to be activated under PDO
Assignment. In this case all PDOs greater than 0x164F (SM0) or 0x174F (SM1) have to be deactivated.
Matching of oversampling factor/process data
If the number of process data does not match the oversampling factor n, the terminal will reach the
OP state, but no process data will be created.
Sample:
Sample for setting a Shift Time:
Under SYNC0 Shift Time User-defined (Fig.
DC tab, activation „Advanced Settings…“, „Distributed Clocks“
),
enter a time as required. Any value that may have been created automatically by the EtherCAT master can
be overwritten, although it should be taken into account in the calculation.
Sample: A value of "-5" is preset. An additional shift of +10 µs is required. -5 + 10 = +5 is entered as new
value.
All time-based/distributed clock-based interrupts (SYNC0/SYNC1) are now offset by this amount relative to
other EtherCAT slaves.
Summary of Contents for EL47 Series
Page 1: ...Documentation EL47xx Analog output terminal with oversampling 2 7 2020 02 27 Version Date...
Page 2: ......
Page 33: ...Mounting and wiring EL47xx 33 Version 2 7 Fig 23 Other installation positions...
Page 70: ...Commissioning EL47xx 70 Version 2 7 Fig 73 Incorrect driver settings for the Ethernet port...
Page 149: ...Commissioning EL47xx 149 Version 2 7 Fig 184 Process data tab SM1 EL47xx...