background image

13

Manual Manifold

2006230.03

2.5  Installation check

2.5.1  Ensure that all tailpipes are connected to the 

gas cylinders and manifolds on both sides and that the 

restraining chains are secure around the cylinders.

2.5.2  Isolate the panel from the pipeline by closing 

the line valve ‘A’ shown in 

figure 8

.

2.5.3  Using one cylinder per side, slowly pressurise 

the control panel 

(see section 4.6 - Cylinder operation)

The bank content gauge should indicate full cylinder 

pressure. The distribution system pressure gauge 

on the regulator (adjust as necessary, see section 

3.3.2) should read typically as per 

table 5

 

(Section 4 - 

Principle  of Operation)

.

 

CAUTION: If the control panel is used as a 

emergency reserve manifold (ERM) it is recommended 

to set the line pressure at least 0.2 bar below the 

main supply source pressure at full design flow to 

ensure the emergency manifold does not supply the 

pipeline during normal primary source operation.

2.5.4  Check for leaks.  Now ensure all bank cylinders 

are closed.

2.5.5  Slowly open the test point valve ‘C’, see

 figure 

8

.  The duty bank of cylinders should drain to typically 

14-25 bar depending on the contact gauge switch point 

(see table 2)

.  After which the contact gauge should 

trigger. This will send a signal to notify that cylinders 

are empty and require changing.  If the control panel 

is not currently connected to an alarm, this can be 

checked with a multimeter across the contacts which 

will change from a closed to an open circuit.

3. Commissioning

3.1 General

Commissioning of the control manifold must be 

carried out in full after initial installation. The object 

of the commissioning procedure is to ensure that 

all components are serviceable and that the overall 

system is operable and set to the correct distribution 

pipeline pressure. Suitably qualified competent 

personnel who are familiar with this manual must 

only undertake commissioning of the panel.

3.2 Preparation

3.2.1  Ensure that all tailpipes are connected to the 

cylinders and manifolds on both sides and that the 

restraint chains are secure around the cylinders.

3.2.2  Ensure that the outlet pipeline connection 

from the manifold panel is connected to the 

distribution system of the same gas service, and 

isolation valve ‘A’

 (see figure 8)

 is present and closed.

3.2.3  Ensure that the panel’s isolation valve ‘C’ 

(shown in figure 8) is installed and in the closed 

position.

3.2.4  Open all cylinder valves on the duty bank and 

close all cylinders on the standby bank.

3.2.5  Check connections on the headers, tailpipes,    

regulator and associated pipework for leaks.

3.3  Pressure Checks

3.3.1  Ensure that full gas cylinder pressure is shown 

on the cylinder content gauges (see figure 8). 

3.3.2  With Valve ‘A’ closed exhaust a small amount 

of gas from the sampling outlet valve ‘C’.  Check that 

the pressure on the pipeline distribution pressure 

gauge is typically as per

 table 5

. Adjust as necessary.

Note - The line regulator is of the non-relieving type 

as required for medical gas control.  Any excess gas 

pressure needs to be manually exhausted in order 

to see the effects of reducing the regulator set point.  

This is achieved by slightly opening the sampling 

outlet isolation valve ‘C’ to produce a gentle bleed 

from the panel.  

3.3.3  Complete the steps in 

section 4.4

 - Procedure 

to prime the control panel, to bring the unit online.

Figure 8 - Manual Manifold Controls

Supply line 

valve ‘A’

Test valve ‘C’

Cylinder 

contents 

gauge

Optional  cylinder bank valves

Line regulator

2.5.6  The installation must now be purged as per 

HTM 02-01 for UK installations, or as per relevant 

standards if installed outside the UK.  

Summary of Contents for Manfiold

Page 1: ...Operation and Maintenance Instructions Manifold Control Systems Manual Manfiold Part number 2006230 Revision 03 May 24 2019...

Page 2: ...Telephone 44 0 1246 474242 Email gbn info beaconmedaes com Website Contacts www beaconmedaes com BeaconMed s reserves the right to make changes and improvements to update products sold previously with...

Page 3: ...Relief Valve Inspection 10 Cylinder Connection 6 Component Replace ment Procedures 11 Line Non return Valve Replacement 12 Test Sampling Point Valve Replace ment 13 2nd Stage Regulator Replacement 14...

Page 4: ...ance must be fully trained in specialist work of this nature Oil grease and jointing compounds must not be used Do not attempt to prove the pressure relief valve under any circumstances by altering th...

Page 5: ...ank valves 15 Single Line contact Module Not shown 16 Double Line contact Module Not shown 17 Manifold Headers C W NRVs 18 Tailpipes Notes Item 11 is recommended for indoor installations Item 15 16 ar...

Page 6: ...ption Part Number Exhaust Pipe Connection Kit 2006233 Termination Box For Remote Alarm 2006219 4 Bar Pressure Switch with Line Contact Monitor 1829936 4 bar Pressure Switch without Line Contact Monito...

Page 7: ...linder headers and tail pipes See table 4 for list of standard manifold assemblies Note tailpipes are supplied separate and may vary depending on required national standards enquire for details Additi...

Page 8: ...and N2O O2 mix Entonox CAUTION Supplied fixings are for use with solid masonry type walls only Typical panel weight is 15kg selected fasteners are suitable for supporting the typical 15 kg weight of...

Page 9: ...stall the first pipe support to the supplied 22mm OD stub pipe Item 10 figure 1 The next support fixture should typically be installed within 2m of the first 2 1 9 The 28mm exhaust line Optional suppl...

Page 10: ...h the kit CAUTION Supplied fixings are for use with solid masonry type walls only Typical cylinder header Including bracket is 1 5kg per side 2 3 3 For additional cylinder headers remove the 3 8 BSP b...

Page 11: ...11 Manual Manifold 2006230 03 Note For additional cylinders beyond 6 continue to add the above for either single or double racks...

Page 12: ...inders on medical gas manifolds or medical equipment 2 4 3 Install the cylinder chains to the header brackets using the D link where shown on figure 6 Loop the chain around the cylinder to secure in p...

Page 13: ...overall system is operable and set to the correct distribution pipeline pressure Suitably qualified competent personnel who are familiar with this manual must only undertake commissioning of the pane...

Page 14: ...ves on the empty bank The empty cylinders must then be replaced See section 4 5 for cylinder handling and section 4 6 for cylinder operation 4 2 4 These steps must be repeated for continuous supply 4...

Page 15: ...nts and when most explosions will occur due to adiabatic compression of any oil or grease that may be present 4 6 1 The cylinder valve should be FULLY opened slowly anticlockwise using the appropriate...

Page 16: ...haust connections are flat face unions complete with o ring seals for ease of removal Figure 9 Relief Valve Maintenance Image shown with optional exhaust 5 3 5 Check the line pressure regulator set po...

Page 17: ...eplace tailpipes pressure safety valve pressure regulator high pressure isolation valve isolation valves contact gauges non return valve etc as and when required see section 6 0 CAUTION For emergency...

Page 18: ...part numbers Table 6 2nd Stage Regulator Part Numbers Regulator Nominal Pressure Part Number 4 Bar 2005689 7 Bar 2005690 6 4 1 Complete steps in section 6 1 before carrying out any component replacem...

Page 19: ...ct the 1 connection the 5 8 header connection and the bracket M6 flange nuts as shown in figure 14 and gently remove the unit by sliding it towards you Take care not to damage the seals 6 5 4 Remove t...

Page 20: ...raining the pipe work as shown in figure 16 Pipe line clamps may need to be unfastened to achieve this Figure 15 2nd Stage Relief Valve Replacement 2 x 1 flat face connections O ring P N 2000152 2nd S...

Page 21: ...le 10 for part numbers Table 10 Line Pressure Gauge Part Numbers Nominal Line Pressure Part Number 4 Bar 2005765 7 Bar 2005766 CAUTION Ensure the new gauge has the same scale as the one being replaced...

Page 22: ...ndustrial regulators are recommended to be replaced every 5 years Although the medical standards do not specifically identify the need to replace the regulators within this time scale it is considered...

Page 23: ...CSA 2 4 4 8 10 2000179 O Ring 17 1 I D x 1 6 CSA 2 4 4 8 11 2000152 O Ring 22 1 I D x 1 6 CSA 2 4 4 8 12 2004808 1 4 Bonded Seal 2 4 4 8 13 1824977 3 8 Bonded Seal 2 4 4 8 14 1825637 1 2 Bonded Seal...

Page 24: ...Copco Ltd trading as Atlas Copco Medical Unit 18 Nuffield Way Abingdon Oxfordshire UK OX14 1RL Tel 44 0 1246 474242 www beaconmedaes com 0088 Atlas Copco Airpower n v Boomsesteenweg 957 2610 Wilrijk B...

Reviews: