Safety instructions for operation
Commissioning
Before commissioning, check that all components and documents are
available.
Inspection
Under EN/IEC 60079-17, the owner of electrical systems in hazardous
areas is obliged to have them checked by a qualified electrician to ensure
that they are in a proper condition.
Maintenance
For electrical systems, the relevant installation and operating regulations
must be observed (e.g. Directive 99/92/EC, Directive 2014/34/EC, BetrSichV
or the nationally applicable ordinances EN/IEC 60079-14 and the DIN VDE
0100 series)!
Please observe the national waste disposal regulations for disposal.
Servicing
Regular servicing is not necessary if the device is operated correctly in
accordance with the installation instructions and ambient conditions.
BARTEC recommends annual servicing and inspection.
See Chapter “Maintenance and care”.
Repairs
Repairs on explosion-protected equipment may be done only by authorised
persons working in accordance with the latest developments in technology
and using original spare parts. The applicable provisions must be observed.
Repairs must be carried out in accordance with EN / IEC 60079-19