Operating Manual for 3D Printer BT1.2
23
1
2
3
4
5
4.3
Commissioning
After reading these instructions, installation and correct wiring:
1.
place the printer on anti-vibration pads on a flat surface
2.
check the main switch position - it must be in the off position "0"
3.
connect the network cable to the power connector
4.
connect the mains cable plug to the 230V 50Hz mains (to the socket)
5.
turn on the main switch (position "I")
When the main power switch is pressed, there is a beeping sound and the system starts up. The device is ready.
Note: After start-up, the cooling ventilator (FAN0) in the control board cabinet spins automatically. The ventilator on the
side extruder (FAN1) does not start working until the extruder temperature reaches 45°C.
Initial screen appearance after booting the system (see the figure below).
MAIN SWITCH