DISCHARGE ..................

4” 125lb Flange, Horizontal

LIQUID TEMPERATURE .

104°F (40°C) Continuous

MOTOR HOUSING ........

Cast Iron ASTM A-48, Class 30

VOLUTE .........................

Cast Iron ASTM A-48, Class 30

SEAL PLATE .................

Cast Iron ASTM A-48, Class 30

IMPELLER:

 

Design

 ...........

2 Vane, Open with Pump out vanes 

 

on Back side. Dynamically 

 

balanced, ISO G6.3

 

Material

 ........

Cast Iron ASTM A-48, Class 30

SHAFT ............................

416 Stainless Steel

SQUARE RINGS ............

Buna-N

DIAPHRAGM .................

Buna-N

HARDWARE ..................

300 Series Stainless Steel

LIFTING BAIL ................

304 Stainless Steel

PAINT .............................

Air dry enamel, top coat

 

(Epoxy Optional)

SEAL

 

Design

 ..........

Double Mechanical in oil fi lled

 

 

pressure equalized reservoir

 

Material

 ........

Rotating Faces - Carbon

 

Stationary Faces - Ceramic

 

Elastomer - Buna-N

 

Hardware - 300 series stainless steel

CORD ENTRY ................

40 Ft. (12.1m) Cord, Epoxy sealed 

 

housing with secondary pressure

  

grommet for sealing and strain relief

SPEED ...........................

1150, 1750 & 3450RPM, 

 

60Hz (nominal), 1450RPM, 50Hz

BEARINGS:

 

Upper

 ............... Single Row, Ball, Oil Lubricated

 

 

Load

 ...... Radial

 

Lower

 ............... Single Row, Ball, Oil Lubricated

 

 

Load

 ...... Radial

 

Life

 ................... 50,000 HR L10 Design

MOTOR:

 

Design

 ..........

NEMA L, Single phase, 

 

 

NEMA B, Three Phase Torque Curve,

 

 

Oil Filled, Squirrel Cage Induction

 

Winding

 ........ Class F, Class H Rated Magnet Wire

 

Service Factor

 ........ 1.15

SINGLE PHASE .............

Capacitor Start/Capacitor Run.

 

Requires BARNES Starter/Panel

 

Which includes capacitors and 

 

overload protection

THREE PHASE ..............

200-240/480, 60Hz is Tri voltage

 

motor. 380-415, 60Hz Dual voltage.

 

Requires overload protection

  

to be included in control panel, VFD  

 

Suitable

MOISTURE SENSOR ....

N/O, Requires relay in control panel

TEMP. SENSOR .............

N/C, Requires relay in control panel

OPTIONAL EQUIPMENT ..

Seal Material, Impeller Trims, 

 

Additional Cord, Epoxy Paint

SECTION: A - PUMP SPECIFICATIONS:
4SE-L and 4SEU-L Pump Models

inches

(mm)

IMPORTANT !

1.)  PUMP MAY BE OPERATED “DRY” FOR EXTENDED PERIODS WITHOUT DAMAGE TO MOTOR AND/OR SEALS. 
2.)  THIS PUMP IS APPROPRIATE FOR THOSE APPLICATIONS SPECIFIED AS CLASS I DIVISION II HAZARDOUS LOCATIONS. 
3.)  THIS PUMP IS NOT APPROPRIATE FOR THOSE APPLICATIONS SPECIFIED AS CLASS I DIVISION I HAZARDOUS LOCATIONS.
4.)  INSTALLATIONS SUCH AS DECORATIVE FOUNTAINS OR WATER FEATURES PROVIDED FOR VISUAL ENJOYMENT MUST BE INSTALLED IN 
 

ACCORDANCE  WITH THE NATIONAL ELECTRIC CODE ANSI/NFPA 70 AND/OR THE AUTHORITY HAVING JURISDICTION. THIS PUMP IS NOT 

 

INTENDED FOR USE IN SWIMMING POOLS, RECREATIONAL WATER PARKS, OR INSTALLATIONS IN WHICH HUMAN CONTACT WITH PUMPED 

 

MEDIA IS A COMMON OCCURRENCE.

Summary of Contents for 4SE-HL Series

Page 1: ...reserves the right to change product without prior written noti cation 420 Third Street 83 West Drive Bramton Piqua Ohio 45356 Ontario Canada L6T 2J6 Phone 937 778 8947 Phone 905 457 6223 Fax 937 773...

Page 2: ...8 20 CROSS SECTION 3450RPM Fig 12 21 EXPLODED VIEW 3450RPM Fig 13 22 PARTS LIST 23 24 RETURNED GOODS POLICY 25 WARRANT START UP REPORT WARRANTY REGISTRATION SPECIAL TOOLS AND EQUIPMENT INSULATION TEST...

Page 3: ...insert ngers in pump with power connected Always wear eye protection when working on pumps Make sure lifting handles are securely fastened each time before lifting DO NOT operate pump without safety d...

Page 4: ...ge Induction Winding Class F Class H Rated Magnet Wire Service Factor 1 15 SINGLE PHASE Capacitor Start Capacitor Run Requires BARNES Starter Panel Which includes capacitors and overload protection TH...

Page 5: ...Cage Induction Winding Class F Class H Rated Magnet Wire Service Factor 1 15 SINGLE PHASE Capacitor Start Capacitor Run Requires BARNES Starter Panel Which includes capacitors and overload protection...

Page 6: ...nits are self contained and are recommended for use in a sump lift station or basin This pump is designed to pump sewage ef uent or other nonexplosive or noncorrosive wastewater and shall NOT be insta...

Page 7: ...e situations may induce a false signal in the moisture detecting circuit If none of the above test prove conclusive the pump s should be pulled and the source of the failure identi ed and repaired IF...

Page 8: ...0 7 32 0 10 4 SOW 0 75 4SE11364L 11 3 200 3 1750 B 32 2 109 5 8 4 SOW 0 83 0 35 4SE11334L 11 3 230 3 1750 D 28 0 126 0 8 4 SOW 0 83 0 43 4SE11344L 11 3 460 3 1750 D 14 0 63 0 8 4 SOW 0 83 1 72 4SE1135...

Page 9: ...n oil into a clean dry container In separate container drain seal chamber by removing pipe plug 22 2 Check oil for contamination using an oil tester with a range to 30 Kilovolts breakdown 3 If oil is...

Page 10: ...ed in paragraph F 2 1 and disassemble seal plate and shaft seal as outlined in paragraph F 4 1 Drain oil from motor as outlined in paragraph F 1 3 Position unit upright using blocks to avoid resting u...

Page 11: ...46 remove impeller 28 as outlined in paragraph F 2 1 Drain oil from seal chamber as outlined in paragraph F 1 3 Remove cap screws 8 and lifting strap 7 Set unit upside down on blocks to avoid damaging...

Page 12: ...pusher until retainer engages spring 46C and spring is compressed slightly Make sure spring 46C is properly engaged in both retainers Slide seal plate 25 over shaft onto bearing bracket 21 being care...

Page 13: ...8 White 3 9 T4 T5 T6 Together THREE PHASE 480 600 VOLT AC Power Cable Motor Lead Number Green Ground Green Black 1 Red 2 White 3 T4 T7 Together T5 T8 Together T6 T9 Together MOISTURE AND TEMPERATURE S...

Page 14: ...e design con guration This number is used for ordering and obtaining information G 3 MODEL NUMBER This designation consists of numbers and letters which repre sent the discharge size series horsepower...

Page 15: ...impeller for freedom of operation security and condition Clean impeller and inlet of any obstruction 9 Loosen union slightly to allow trapped air to escape Verify that turn off level of switch is set...

Page 16: ...16 FIGURE 10 4SEU Models ONLY 4SE 4SEU Pump Series...

Page 17: ...17 FIGURE 11 4SE 4SEU Pump Series...

Page 18: ...8 2 1 68 1 Cap Screw 1 2 13 x 1 1 4 lg Stainless 10 1 See Table 2 Conduit Box Cable Assembly 10a 1 Power Cable Not Sold Separately 10b 1 051447 Gland Nut 1 072559 Gland Nut For 7 5 11 3Hp 3Ph 15Hp 57...

Page 19: ...1150RPM 8 75 Dia 084894TS 084895TS 8 62 Dia 084894TT 084895TT 15HP 1750RPM 8 50 Dia 084894TU 084895TU 8 38 Dia 084894TV 084895TV 8 25 Dia 084894TW 084895TW 8 12 Dia 084894TX 084895TX 11 3HP 1750RPM 8...

Page 20: ...ring 53 5 016405 t Insulator 5 030149 t Insulator 7 5HP 1PH 15HP ONLY 54 1 052761 Wear Plate 4SEU s ONLY 55 4 1 130 1 Cap Screw 5 16 18 x 1 0 lg Stainless 56 4 20 2 1 Lockwasher 5 16 Stainless TABLE 2...

Page 21: ...21 4SE HL High Ef ciency Pump Series FIGURE 12...

Page 22: ...22 4SE HL High Ef ciency Pump Series FIGURE 13...

Page 23: ...on Ring 2 071431A Friction Ring For 7 5 11 3Hp 3Ph 15Hp 575V 2 110929 Friction Ring For 7 5HP 1PH 15HP ONLY 10d 1 051452 Grommet 1 071430A Grommet For 7 5 11 3Hp 3Ph 15Hp 575V 1 110928 Grommet For 7 5...

Page 24: ...ess 39 2 036803 Soc Hd Cap Screw 1 4 20 x 3 4 lg Stainless 41 1 036852 t Gasket 42 1 056668 t Square Ring 43 1 022879 Diaphragm Clamp Ring 44 4 002203 Cap Screw 1 4 20 x 7 8 lg Steel 46 1 039485 t Sha...

Page 25: ...s between the results of eld testing conducted by or for user and laboratory tests corrected for eld performance the latter shall control RECOMMENDATIONS FOR SPECIAL APPLICATIONS OR THOSE RESULTING FR...

Page 26: ...nt To Insure That Employees Will Not Be Exposed To Health Hazards In Handling Said Material All Applicable Laws And Regulations Shall Apply IMPORTANT WARRANTY REGISTRATION Your product is covered by t...

Page 27: ...O___ Type _________________________________ Number and size of short circuit device s ___________ Amp rating ___________________ Overload Type _____________ Size ______________ Amp rating ____________...

Page 28: ...rols installed away from turbulence YES___ NO___ Is level control operating properly YES___ NO___ Is pump fully submerged during operation YES___ NO___ Follow up Corrective Action Required YES___ NO__...