Software • B&R Automation Device Interface (ADI) - Control Center
256
Panel PC 800 User's Manual V1.30
Figure 138: ADI Control Center - UPS battery settings
This window can be used to change the settings for the UPS battery.
Click
OK
to write the changed settings to the file. The battery settings for the UPS can then be updated with this file.
Information:
To make settings for non-B&R batteries, it is best to make a copy of a file that contains battery settings
from B&R under a new name and then adjust the settings in this new file for the battery being used.
Current files with settings for batteries from B&R can be updated using B&R's "Upgrade PPC800 MTCX" software.
Information:
•
The current UPS firmware version 1.10 does not use charge end voltage, deep discharge volt-
age, service life and deep discharge cycles.
•
Service life is only included in version 2 (and higher) of the UPS battery settings and only valid
for B&R UPS batteries at 25°C ambient temperature.
•
Deep discharge cycles are only included in version 3 (and higher) of the UPS battery settings
and only valid for UPS batteries from B&R.
Information:
To change the current battery settings on the UPS, they must first be saved to a file.
11.4.4 Updating UPS battery settings
1. Open the
Control Center
in the
Control Panel
.
2. Select the
UPS
tab.
3. Under
Battery settings
, click on
Update
. Clicking on "Open" opens a dialog box.
4. Select and
open
the file containing the battery settings. The "Download" dialog box is opened.
The transfer can be canceled by clicking on
Cancel
. "Cancel" is disabled when writing to flash memory.
Information:
•
The UPS cannot be operated while the battery settings are being updated.
•
If the transfer is aborted, then the procedure must be repeated until the battery settings have
been updated successfully. Otherwise, battery operation will no longer be possible.