14 / 38
23346-002 en/2023-03
4
Preparation for operation
4.1 Installation site requirements
The installation location of the device must meet the following conditions:
• The installation surface must be horizontal, firm and dry.
• The load-bearing capacity must be sufficient for the device with sonication fluid.
For weight and work content, see chapter
.
• Adequate ventilation must be ensured. The air supply under the bottom of the device
may not be obstructed.
• A water connection should be available nearby to fill the device. A basin must be available
to drain or pour out the sonication fluid.
Procedure
1. Remove all transport aids, such as pallets and transport locks.
2. Install the supplied height-adjustable feet on the bottom of the device.
3. Level the device by adjusting the height-adjustable feet.
Results
» The device is set up.
4.2 Installing ball valves
Install the supplied ball valves, hose connectors and hoses according to the enclosed
installation instructions:
• 3-way ball valve at the outlet
• Ball valve on the overflow
Preparation for operation