STARTING UP AND REGULATION
• Make sure that the mains voltage corresponds to the manufacturer's
requirements and that all electrical connections made at the
installation site are effected properly as illustrated in our wiring
diagram.
•
Make sure that the combustion products may be freely vented
through the boiler and flue dampers.
•
Check that there is water in the boiler and that the gate valves of the
system are open.
•
Check that all the gate valves fitted on the fuel suction and return
pipes are open; the same applies to any other fuel shut-off devices.
•
Make sure that the combustion head is long enough to enter the
furnace following the measure specified by the boiler manufacturer.
•
Bleed out the air contained in the gas piping, with due precautions
and with doors and windows open.
•
Open the union on the pipe near the burner and then open slightly
the gas shut-off cocks.
When the characteristic odour of gas can be smelled, close the cut-off
cock.
• Wait the time necessary for the gas in the room to disperse outside.
Re-connect the burner to the gas pipeline.
I
sinottico_lamtecBT3xx
1
3
5
2
4
1 - Main On / Off switch
2 - Fuse
3 - Display
4 - Confirm or RESET key
5 - Programming keys
•
Install a pressure gauge with adequate scale on the pressure outlet
of the gas pressure switch.
•
With the switch (1) on the mimic panel switched to “O” and the main
switch turned on, manually close the remote control switch and
check that the motor revolves in the correct direction. If necessary,
exchange the position of the two cables in the line that feeds the
motor in order to reverse the direction of revolution.
•
Now switch on the main switch. This powers on the control device,
and the programmer turns on the burner as described in the
chapter "Operation description". For burner adjustment, refer to the
instructions for the electronic cam supplied.
•
When the burner stops, the post-ventilation function is activated and
remains in operation for 120 sec.
•
After having adjusted the “minimum”, (200) turn the burner gradually
to maximum, by using the controls on the electronic cam keyboard.
•
Check combustion (CO, O2, NOx) using the appropriate instrument
at all intermediate points on the modulation route (from 200 to 999),
checking the gas flow rate by reading the meter.
•
Now check the proper automatic operation of modulation. This
ensures that the equipment receives the signal from the electronic
modulation regulator, if the burner is the modulating model, or from
the second stage thermostat or pressure switch, if it is a two stage
progressive burner.
The air pressure switch stops the equipment operation if air pressure
is not at the expected value.
The pressure switch must therefore be adjusted so that it is triggered
to close the NO (normally open) contact when the air pressure in the
burner reaches the set value.
The connection circuit of the pressure switch is self-controlling so
that the NC contact (normally closed) which is meant to be closed at
rest (with the fan stopped and consequent lack of air pressure in the
burner), is actually in this condition. If it is not, the control box is not
switched on and the burner does not start.
19 / 34
0006081328_202202
ENGLISH
Summary of Contents for TBG 80 LX ME
Page 2: ......
Page 32: ...SCHEMI ELETTRICI TBG 80 360LX ME TBG 80 360 ME 30 34 0006081328_202202 ITALIANO...
Page 33: ...TBG 80 360LX ME TBG 80 360 ME 31 34 0006081328_202202 ITALIANO...
Page 34: ...TBG 80 360LX ME TBG 80 360 ME I1 I2 BA I4 I3 32 34 0006081328_202202 ITALIANO...
Page 36: ...34 34 0006081328_202202 ITALIANO...
Page 66: ...WIRING DIAGRAMS TBG 80 360LX ME TBG 80 360 ME 30 34 0006081328_202202 ENGLISH...
Page 67: ...TBG 80 360LX ME TBG 80 360 ME 31 34 0006081328_202202 ENGLISH...
Page 68: ...TBG 80 360LX ME TBG 80 360 ME I1 I2 BA I4 I3 32 34 0006081328_202202 ENGLISH...
Page 70: ...34 34 0006081328_202202 ENGLISH...
Page 71: ......