8 / 24
0006081484_201104
EN
GL
IS
H
BURNER CONNECTION TO THE
BOILER
ASSEMBLING THE HEAD UNIT
- Position insulating seal 3 on the sleeve, placing
cord 2 between the flange and the seal.
- Loosen screws “6”, adjust the position of the
connection flange “5” so that the combustion
head penetrates the furnace up to the length
recommended by the generator manufacturer.
- Referring to the diagram at the side, fit the rigid
pipe in the housing provided on the connection
flange and fasten it with the screw. This pipe will
be cut flush with the diffuser.
Fasten the burner 4 to the boiler 1 by means of
the stud bolts, washers and the nuts provided 7.
!
Completely seal the space between the
burner sleeve and the hole in the refrac-
tory material inside the boiler door with
suitable material.
Rigid pipe fixing screw
Rigid pressure detection pipe in the combustion chamber
Pressure tap in
the combustion
chamber
Cut flush with diffuser
Pressure transmission pipe in the combustion chamber
ASSEMBLING THE GAS TRAIN
There are different ways of assembling the valve train
8, 8a, 9, as shown in the drawing.
Choose the most rational position for the set-up of
the boiler room and the position in which the gas
pipe arrives.
Summary of Contents for TBG 45 PN-V
Page 2: ......
Page 26: ...24 24 0006081484_201104 ENGLISH ...
Page 50: ...24 26 0006081484_201104 ESPAÑOL ...
Page 74: ...24 26 0006081484_201104 FRAÇAIS ...
Page 98: ...24 24 0006081484_201104 TÜRKÇE ...
Page 123: ...123 126 0006081484_201104 ...