20
PARTS REQUIRED:
x100
2" (5,1 cm)
8' WALL 02
Install all panels with the primed side facing up.
48 x 84"
(121,9 x 213,4 cm)
x2
3/4" GAUGE
BLOCK
GAA
2x4
TEMP. SPACER
2
Install (1)
48 x 84"
panel on wall
frame 1-1/2" from the top plate.
Use a 2x4 spacer for
consistent measurement.
Use the gauge block
to mark the 3/4" measurement
on the wall stud.
Secure the panel with 2" nails
spaced 6" apart on edges and 12"
apart inside panel.
FINISH
3
Your 8' WALL 02 is now assembled.
Carefully flip the gable wall over.
Install next
48" x 84"
panel
flush to installed panel.
Locate panel 1-1/2" from
the top plate.
Use a 2x4 spacer for
consistent measurement.
Secure with 2" nails spaced 6"
apart on edges and 12"
apart inside panel.
2x4
6"
(15,2 cm)
6"
(15,2 cm)
1-1/2"
(3,8 cm)
12"
(30,5 cm)
12"
(30,5 cm)
2x4
Flush
Flush
1-1/2"
(3,8 cm)