7
Unit Rigging & Assembly
Multi-Cell Installation
Multi-Cell Unit Assembly
Flume Box Installation
Cell #1
Cell #2
Figure 8.
Flume Box Installation
2 Layers Of Flat
Sealer Tape
Apply Flat Sealer Tape
Over The Center Line
of the Bolt Holes
Detail A
NOTE:
For cold water basins
constructed with the TriArmor
®
Corrosion Protection System, attach
the vertical and horizontal backing
plates as shown in
Figure 10,
Detail A.
2 Layers of Flat
Butyl Sealer Tape
A
A
Cell #1
Cell #2
3/8" S.T. Screw
2 Layers of Flat
Butyl Sealer Tape
Flume Box
Cell #1
Cell #2
2 Layers of Flat
Butyl Sealer Tape
Figure 9.
Expanded View
Figure 10.
Elevation View
2 Layers of Flat
Butyl Sealer Tape
A
A
Cell #1
Cell #2
3/8" S.T. Screw
2 Layers of Flat
Butyl Sealer Tape
Flume Box
Cell #1
Cell #2
2 Layers of Flat
Butyl Sealer Tape
2 Layers of Flat
Butyl Sealer
Tape
SST 3/8 X 1/4
Bolt (Typ.)
Flume Box
Backing Plates Used on
TriArmor® Basins Only
SST 3/8
Flatwasher (Typ.)
No Sealer Between
Backing Plates
and Basin Wall
Basin Wall
Detail A.
For Units with TriArmor
®
Corrosion Protection System Only
6. Apply two layers of flat butyl sealer tape to the other end of the flume box.
7. Wipe down the surface adjacent to the flume opening of Cell #2 to remove any
dirt or moisture. Position Cell #2 on the unit supports.
8. Using drift pins to assure alignment, draw Cell #2 tight against the flume box.
9. Repeat Step 5 to fasten the flume box to Cell #2.