![BAC 3000 Series Rigging & Assembly Instructions Download Page 15](http://html1.mh-extra.com/html/bac/3000-series/3000-series_rigging-and-assembly-instructions_3287014015.webp)
13
Unit Rigging & Assembly
Top Inlet Piping Installation
Figure 16.
Single Riser Piping Schematic
Figure 17.
Dual Riser Piping Schematic
Plan View
Elevation View
C (Typ. Per Cell)
Water Inlet
(See Unit Print For Size)
See Figure 18, Detail C
See Note 5
Static Lift
B
A
H
NOTES FOR FIGURE 17:
1.
All piping shown by dashed
lines is to be furnished by
others. Refer to the certified
unit print for details on the
cooling tower.
2.
Field piping should be
fabricated at the time of unit
installation. Pre-fabrication of
pipe work is not recommended.
3.
Required static pumping head
from base of cooling tower
is indicated by static lift
dimension and piping friction
losses.
4.
When tower is equipped with
safety railing package, inlet
piping should be designed to
clear the railing. Adjust static
lift as required.
5.
For units installed on vibration
isolation rails (provided by
others), flexible connections
should be installed in the
piping just before the tower
perimeter.
6.
All piping supports to be
designed, furnished, and
installed by others.
7.
Supply piping to the cooling
tower inlet connections must
not be supported from the
tower.
Piping by others. Fl ow control valves availab le by BAC or others, and always install ed by others.
1 1/2” x 12” (PLA TE) AND PIPE
SUPPORT - (BY OTHERS)
DETAIL “A”
PIPE SUPPORT AT END OF TOWER
(SEE NOTES 7 & 8)
DETAIL “ B”
PIPE SUPPORT BETWEEN TOWER
(SEE N OTES 7 & 8)
6 3/4” X 12” (PL ATE)
AND PIPE SUPPORT
(BY OTHERS)
DETAIL “C”
FACE OF WATER INLET AT HOT WATER
DISTRIBUTION BASIN
FACE
OF
WATER
INLET
STUD PATTERN
(BY BAC)
PIPING
(BY OTHERS )
PIPING
BY
OTHERS
FL OW CONTRO L
VALVE (BY BAC
OR OTHERS)
MIN.
RECOMMENDED
8” FROM FACE TO
FACE OF FLANGE
Figure 18.
Piping Drawing Details