2.  Place housing in hole. Align junction box in the 

path of the conduit trench.

3.  Insert (4) pieces of ½” EMT conduit through the 

Stability Flange™. Hammer into substrate  until 

secure.

Leave sufficient clearance to elevate housing 

to finished grade.

4.    To accommodate the overhang and allow for 

proper sealing between the faceplate and 

housing, you’ll need to 

elevate the housing at 

least a 1/4”

 above the finish grade. Use a level  

to aid in leveling housing.  

5.  When housing is level, tighten screws on 

Stability Flange™ to secure housing to EMT. 

Remove excess EMT as needed.

Housing Installation

Threaded Entry

Side Flats

1.  Connect branch conduit connectors (By Others) 

to the junction box using either the threaded 

conduit entries on the bottom of the junction 

box or through holes drilled into the sides of the 

junction box. 

6.  Connect the conduit to the conduit connectors. 

7.   Pull primary branch circuit wiring into junction 

box.  

IMPORTANT SAFETY INFORMATION LISTED ON REVERSE

READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS

CO

2

 SERIES

Inspiration Control System

 Installation Instructions

iOS device (Not Included) with installed B-K Lighting Inspiration Application required for use.

Soil Prep

Conduit
trench

18”

Dia.

A.  Determine Soil Type by referencing DIG-IT 

Guide. 

B.  Dig hole 18” wide and 20” deep.

Conduit
Trench

Excavated 
for Housing

C.  Prep soil according to DIG-IT Guide.