Figure 9 

Positive Closure Plate Option

The optional Positive Closure Plate and gasket can be furnished on
multi-cell units to allow individual cells to be isolated for cleaning
and routine maintenance.  For PT2 Cooling Towers, the plate ships
loose inside the basin.  To install the Positive Closure Plate and 
gasket, follow the steps that correspond to your unit from the 
“Assembly of Multi-Cell Towers” section; then complete the 
installation of your specific type of unit using the instructions listed. 

Positive Closure Plate Installation (Figures 9 and 10):

1.  Thread 3/8” self-tapping screws from the flume box into 

the  basin wall with the positive closure plate as shown 

2.  Position the neoprene gasket and positive closure plate 

over the bolts and fasten in place  with 3/8” wing nut 
and flat washers

Water Baffles

For multi-cell PT2 Cooling Towers, water baffles join the air louver sections to prevent leaks.  To 
install the water baffles, follow the steps below.

Water Baffle Installation (Figure 11):

1.  Slide lower water baffle into place  

2.  Install left and right side water baffles by first aligning top notches and then sliding bottom 

into place.  Install 3/8” self-tapping screws in each hole provided 

Figure 8

Figure 10

Figure 11

6

Summary of Contents for PT2

Page 1: ...uld be checked thoroughly to ensure all required items have been received and are free of any shipping damage prior to signing the bill of lading The following parts should be inspected Sheaves and Belts Bearings Bearing Supports Fan Motor s Fan s and Fan Shaft s Fan Guard s Float Valve Assembly s Water Distribution System Fill Cold Water Basin Strainer s Interior Surfaces Exterior Surfaces Louver...

Page 2: ...s equipment Proper care procedures and tools must be used in handling lifting installing operating maintaining and repairing this equipment to prevent personal injury and or property damage Freeze Protection Cooling towers must be protected by mechanical and operational methods against damage and or reduced effectiveness due to possible freeze up Please refer to the Product and Applications Handbo...

Page 3: ...le Section Upper Section Upper Section One Piece PT2 Model Number H distance from lift point to lifting device in feet Lower Section Upper Section PT2 0412 16 8 PT2 0709 14 10 PT2 0809 14 12 PT2 0812 16 12 PT2 1009 14 14 PT2 1012 16 14 PT2 1212 16 16 Figure 3 shows the proper rigging and assembly of units that ship in three sections optional 3 Figure 1 Figure 3 Figure 2 H H H H H ...

Page 4: ...y a layer of 1 8 x 1 foam tape around the face of the flange over the centerline of the holes As illustrated in Figure 4 insert 3 8 self tapping screws in each hole from the upper section into the middle section and tighten Note On quad installations it is suggested that cells subsequent to the first have the upper and lower sections assem bled on the support foundation adjacent to the final mount...

Page 5: ...ng the same procedure Refer to Figure 6 4 Using drift pins to align the bolt holes place the flume box over the opening in the basin of Cell 1 and fasten into place Insert the 3 8 self tapping screws or bolts from the flume box into the basin wall as illustrated in Figure 7 Note Flume boxes furnished with units constructed with stainless steel basins are assembled with stainless steel bolts washer...

Page 6: ...sure Plate Installation Figures 9 and 10 1 Thread 3 8 self tapping screws from the flume box into the basin wall with the positive closure plate as shown 2 Position the neoprene gasket and positive closure plate over the bolts and fasten in place with 3 8 wing nut and flat washers Water Baffles For multi cell PT2 Cooling Towers water baffles join the air louver sections to prevent leaks To install...

Page 7: ...ections 90 apart The piping connection is a bolt circle designed to fit an ASME Class 150 flat flange with a full face gasket To install the side outlet depressed sump box follow the steps below 1 Wipe the edges around the opening in the cold water basin to remove any dirt or moisture that may have accumulated during shipment Apply a layer of 1 8 x 1 butyl sealer tape around the opening in the bas...

Page 8: ...tainless Steel Nema 3R terminal box see Figure 16 for the exterior location of the box on the tower The box includes a cover plate which once removed reveals an easy to follow wiring diagram and modular terminal blocks Remove the cover plate and install the collar which ships in the tower s cold water basin which has pre punched conduit holes Wiring from the terminal blocks to the unit controls is...

Reviews: