WARNING:  In the event of extended lifts or where hazards exist, the lifting devices should be used in conjunction with
safety slings placed under the unit.

Anchoring

Seven-eighths inch (7/8”) diameter holes are provided in the bottom flange of the basin section for
bolting the unit to the support beams.  Refer to the suggested support location drawing included in
the submittal for location and quantity of the mounting holes.  The unit must be level for proper 
operation.  Anchor bolts must be provided by others.  IBC rating is only certified with standard 
anchorage locations.  Using alternate anchorage locations, alternate steel supports or vibration 
isolation rails will void any IBC wind or seismic ratings. 

Safety

Adequate precautions appropriate for the installation and location of these products should be taken
to safeguard the equipment and the premises from damage and the public from possible injury.

WARNING:  When the fan speed of the unit is to be changed from the factory set speed, including the use of a variable
speed device, steps must be taken to avoid operating at or near the fan’s “critical speed” which could result in fan failure
and possible injury or damage.  Consult with your local BAC Representative on any such applications.

WARNING:  Only personnel qualified to do so should undertake operation, maintenance and repair of this equipment.
Proper care, procedures and tools must be used in handling, lifting, installing, operating, maintaining and repairing this
equipment to prevent personal injury and/or property damage.

Freeze Protection

Cooling towers must be protected by mechanical and operational methods against damage and/or 
reduced effectiveness due to possible freeze-up.  Please refer to the Product and Applications 
Handbook, Operation and Maintenance Manual or contact your local BAC Representative for 
recommended protection alternatives.

Location

All evaporative cooling equipment must be located to ensure an adequate supply of fresh air to the
fans.  When units are located adjacent to walls or in enclosures, care must be taken to ensure the
warm, saturated, discharge air is not deflected and short-circuited back to the air intakes.

CAUTION:  Each unit must be located and positioned to prevent the introduction of discharge air into the ventilation sys-
tems of the building on which the unit is located and of adjacent buildings.  For detailed recommendations on BAC equip-
ment layout, see our website at www.BaltimoreAircoil.com or contact your local Representative. 

Warranties

Please refer to the Limitation of Warranties applicable to and in effect at the time of the sale/purchase
of these products.

Rigging

Refer to Table 1 for the recommended vertical dimension “H” from the lifting device  to the spreader
bar.  In the event of extended lifts or where hazards exist, the lifting devices should be used in con-
junction with safety slings placed under the unit.

2

Summary of Contents for PT2

Page 1: ...uld be checked thoroughly to ensure all required items have been received and are free of any shipping damage prior to signing the bill of lading The following parts should be inspected Sheaves and Belts Bearings Bearing Supports Fan Motor s Fan s and Fan Shaft s Fan Guard s Float Valve Assembly s Water Distribution System Fill Cold Water Basin Strainer s Interior Surfaces Exterior Surfaces Louver...

Page 2: ...s equipment Proper care procedures and tools must be used in handling lifting installing operating maintaining and repairing this equipment to prevent personal injury and or property damage Freeze Protection Cooling towers must be protected by mechanical and operational methods against damage and or reduced effectiveness due to possible freeze up Please refer to the Product and Applications Handbo...

Page 3: ...le Section Upper Section Upper Section One Piece PT2 Model Number H distance from lift point to lifting device in feet Lower Section Upper Section PT2 0412 16 8 PT2 0709 14 10 PT2 0809 14 12 PT2 0812 16 12 PT2 1009 14 14 PT2 1012 16 14 PT2 1212 16 16 Figure 3 shows the proper rigging and assembly of units that ship in three sections optional 3 Figure 1 Figure 3 Figure 2 H H H H H ...

Page 4: ...y a layer of 1 8 x 1 foam tape around the face of the flange over the centerline of the holes As illustrated in Figure 4 insert 3 8 self tapping screws in each hole from the upper section into the middle section and tighten Note On quad installations it is suggested that cells subsequent to the first have the upper and lower sections assem bled on the support foundation adjacent to the final mount...

Page 5: ...ng the same procedure Refer to Figure 6 4 Using drift pins to align the bolt holes place the flume box over the opening in the basin of Cell 1 and fasten into place Insert the 3 8 self tapping screws or bolts from the flume box into the basin wall as illustrated in Figure 7 Note Flume boxes furnished with units constructed with stainless steel basins are assembled with stainless steel bolts washer...

Page 6: ...sure Plate Installation Figures 9 and 10 1 Thread 3 8 self tapping screws from the flume box into the basin wall with the positive closure plate as shown 2 Position the neoprene gasket and positive closure plate over the bolts and fasten in place with 3 8 wing nut and flat washers Water Baffles For multi cell PT2 Cooling Towers water baffles join the air louver sections to prevent leaks To install...

Page 7: ...ections 90 apart The piping connection is a bolt circle designed to fit an ASME Class 150 flat flange with a full face gasket To install the side outlet depressed sump box follow the steps below 1 Wipe the edges around the opening in the cold water basin to remove any dirt or moisture that may have accumulated during shipment Apply a layer of 1 8 x 1 butyl sealer tape around the opening in the bas...

Page 8: ...tainless Steel Nema 3R terminal box see Figure 16 for the exterior location of the box on the tower The box includes a cover plate which once removed reveals an easy to follow wiring diagram and modular terminal blocks Remove the cover plate and install the collar which ships in the tower s cold water basin which has pre punched conduit holes Wiring from the terminal blocks to the unit controls is...