7.2.1 Tools Required
Tools Needed (not supplied)
Flush Cutter
Tongue & Groove Pliers
Silicone Sealant
Cable Jacket Trimmer (optional)
Utility Knife
Electrical Tape
Insulated Terminal Crimper
Wire Strippers 10AWG to 18AWG Range
2.5mm Hex Key
2.0mm Flat Blade Precision Screwdriver
#2 Phillips Screwdriver
Mounting hardware (optional purchase)
Cables (owner supplied or optional purchase)
7.2.3 Factory Configuration
•
External Photocell wired with 7.5 metre flying lead.
•
Preassembled T2 Control Unit complete with internal wiring
7.2.4 Installation Recommendation
Note:
The sequence of steps can be adjusted for site requirements.
1. Wire and test the system on ground level.
Conduct a basic functional check to ensure that the lights turn on as expected. See section
7.3 Testing Procedure