Operation of the power-operated window 

When operating the power-operated window safety
instructions must be observed, specifi cally those pertaining 
to commissioning, operation and maintenance.

Check the mounted system for its safety; perform test run 
and commissioning.

Safety test:

•  Connect operating voltage.
•  Check fastening (frame brackets, casement brackets)
  for fi rm fi t or tightening.

Test run:

•  Visual inspection of casement movements.
•  Stop immediately by malfunction!
•  Pay attention to collision with facade construction and
  correct installation, if required.

Risk evaluation:

Before operating a power-operated window to which 
window drives were mounted, which were sold by the
manufacturer as incomplete machines according to instal-
lation declaration, the possible risk to ahazard of persons 
must be determined, evaluated and minimized by taking 
appropriate technical measures in accordance with the Ma-
chinery Directive. Separate documents for performing a risk 
assessment can be downloaded from the homepage of

Firm 

a

UMÜlleR

 

a

UMatIc

 GmbH

 

(

www.aumueller-gmbh.de

).

S

afety

 

CheCk

 

anD

 t

eSt

 

Run

Formula to calculate

the required wire cross-section of a supply line

Calculation example

Available data:
•  cut-off current per drive (i. e. 2 x 4.0A) from data sheet
•  length to be bridged from the last window to the control unit
     (i. e. 10 meters)

A

I

L

2

2,0

56

mm

2  

=

(total) *

*

*

(length supply line) 

m

(voltage drop) 

m / (Ω*mm

2

)

(2 * 4,0A) * 10m * 2

A =

2,0V * 56m / (Ω*mm

2

)

A =  1,42mm

2

  ->  

1,5mm

2

 chosen

S

uPPly

 

lineS

 

of

 C

ontRol

 u

nit

 

to

 

the

 D

RiVeS

Laying and connecting the drive cable

•  Avoid extreme temperature differences in the instal-
  lation area (danger of condensation).
•  Set clamping point close to window and ensure
 accessibility.
•  Ensure expansion possibilities of the drive and the drive
 cable.
•  Consider the cable length and the cross sections of
  the drives supply lines.

24V

Observe current regulations and guidelines regarding
the “Fire behavior of building materials-circuit integrity
maintenance of electric cable systems“ (E30, E60, E90) and 
the prescribed constructional regulations!

R

eCommenDation

For safety reasons a cable of the next hig-
her wire cross section should be selected. 

I

nstallatIon

 

step

 8:

I

nstallatIon

 

step

 7:

07

 

e

leCtriC

 C

onneCtion

 / s

afety

 C

heCk

Summary of Contents for LKS S2 24V DC

Page 1: ...according to Machinery Directive 2006 42 EC annex VI LKS S2 24V DC Rack and Pinion Drives for windows Assembly and Commissioning Instructions...

Page 2: ...a Assembly drive with frame bracket K29 Installation step 4b Assembly drive with adjustable clamping B7 and frame bracket K82 Installation step 4c Assembly drive with adjustable clamping B7 and frame...

Page 3: ...ng Caution Warning Danger due to electric current Caution Warning Risk of crushing and entrapment during device operati on is provided as a sticker with the drive Attention Warning Risk of damage to d...

Page 4: ...s NSHEV natural smoke and heat exhaust ventilator s in accordance with EN12101 2 without dual purpose for ventilation The need for a risk assessment at the installation site due to the reasonably fore...

Page 5: ...witch strips or Motor current monitoring systems internal and external Hold to run switch stops movement at HSK 20 mm at a closing force of 150 N at HSK 20 ZAA 5 Operating element in direct range of v...

Page 6: ...e electrical supply data see product lable and performance limits see technical data as well as the mounting and installation instructions of the drive must be strictly observed and adhered to Do not...

Page 7: ...able cable lengths and cross sections shall be selected in accordance with the manufacturer s technical data If necessary the cable types shall be coordinated with the competent local authorities and...

Page 8: ...e instructed in all important opera ting steps If necessary he must be advised of all remaining risks dangers The end user shall be specifically instructed that no additional forces except pushing and...

Page 9: ...e and heat exhausting systems SHEV as single drive Internal load dependend cut off switch S2 Options Drillings for front suspension Monitored motion run of 2 drives up to s 300 mm via USKM Order data...

Page 10: ...formation on the most import ant caracteristics such as manufacturer s address article reference number and name technical caracteristics date of manufacturing with firmware version serial number cert...

Page 11: ...2200 2400 2600 Abstand Antrieb Band ffnungswinkel 2 1 3 4 5 6 7 8 9 10 1 Hubl nge 100 mm 2 Hubl nge 200 mm 3 Hubl nge 300 mm 4 Hubl nge 400 mm 5 Hubl nge 500 mm 6 Hubl nge 600 mm 7 Hubl nge 700 mm 8...

Page 12: ...balance The test procedure of drives may only be performed on a non slip and secured mat or a test fixture During the test run the test element must not be interfered with The test my only be conducte...

Page 13: ...2 FAB 1 2 FAB 1 4 FAB 1 4 FAB Tools required Marker Grains Hammer Screwdriver slotted head cross or Torx size by site conditions Hexagonal wrench size 4 5 Fork wrench for SW13 SW14 Torque wrench Power...

Page 14: ...et K82 for swivelling suspension Frame bracket K5 for swivelling suspension Adjustable clamping B7 Mounting with K5 or K82 Frame bracket K21K For moving the mounting level from the horizontal to the v...

Page 15: ...g casement outwards opening Frame assembly HSK View on aluminium window View on PVC window Roof window outwards opening Frame assembly HSK Roof window outwards opening Frame assembly HSK View on alumi...

Page 16: ...associated bolt 6 of the casement brackets F1 into the eyebolt of LKS Optionally adjust the pressure ball of the casement bracket F1 with grub screw and the spring Adjust casement pressure using of th...

Page 17: ...linder head screws M6 of the adjustable clamping B7 Slide the adjustable clamping B7 gently on the drive body LKS by hand do not force Screw the cylinder head screws M6 of the adjustable clamping B7 a...

Page 18: ...e bracket K21K M6 Make sure they are parallel to casement edge Casement bracket center and rack must be in line Determine fastenings for casement bracket F10 6 frame bracket K21K and for frame bracket...

Page 19: ...arefully clear away drilling swarfs to prevent seals from being damaged Avoid surface scratches for example by using masking tape Secure fasteners against loosening e g by applying removable thread lo...

Page 20: ...propriate cross section for mounting dimensions see drill holes Installation stepe 3 or project specific documents and drawings Note Screws for mounting on the window are to be provided by the custome...

Page 21: ...s s 300 mm max 2 5 A IP 54 0 C 70 C 110 x 110 x 66 mm Motion monitoring up to 3 drives 2 sequential controls DIP switches for settings Connection terminals 2 5 mm 24V Installation step 6 Electric conn...

Page 22: ...he homepage of Firm aUM lleR aUMatIc GmbH www aumueller gmbh de Safety CheCk anD teSt Run Formula to calculate the required wire cross section of a supply line Calculation example Available data cut o...

Page 23: ...ear or damages of cables and fastening elements must be performed During maintenance contaminations must be removed from the drive Fastenings and clamping screws must be checked for tightness Test run...

Page 24: ...or delivered material is twelve months Warranty and liability claims for personal injuries or material damages are excluded if caused by one or more of the following No proper incoming goods inspectio...

Page 25: ...25 LKS S2 24V DC Notes 08...

Page 26: ...26 LKS S2 24V DC Notes 08...

Page 27: ...s and Conditions of aUM lleR aUtoMatIc GmbH apply to all offers supplies and services The publication of these assembly and commissioning instructions supersedes all previous editions CeRtifiCate anD...

Page 28: ...9000028501_V0 1_KW05 20...

Reviews: