MAN - BBR2S - REV: Original | D. Installation
14
4. Position the shroud and load nose at the base of the load frame. Lift the load nose and carefully screw it on to the
threaded stud in the bottom of the load cell until it is finger tight. When complete, secure the load nose in place by
tightening the set screw on the side of the load nose (see Figure D.4 and D.5).
WARNING:
Do not over tighten the load nose, or damage to the load cell may occur.
5. Once the load nose is secured, lift the upper portion of the shroud around it. Use the back two screws to guide it
into place before tightening them and carefully screwing in the front two screws. See Figure D.6.
CAUTION: Do not over tighten the load nose on the load cell, or the load cell may become
damaged. The load cell is extremely sensitive to this twisting movement.
CAUTION: The load cell can be easily damaged, especially from side loading and excessive
torque. DO NOT place Load Frame on its side once the Load Nose is in place. Improper
handling will result in irreversible Load Cell damage.
6. To re-attach the lower portion of the load shroud, place the lower portion of the shroud on a flat surface.
CAREFULLY lift the load frame, and position it so that the load nose is directly above the lower portion of the
Figure D.6 - Upper portion of shroud
attached to Load Cell
Figure D.5 - Tightening the Set
Screw
Figure D.4 - Set Screw Location on
Load Nose