Page 7 

Testing & Service 

Transfer Test 

Operate the transfer switch at least once a month by following 
the 

Electrical Operation

 procedure on page 6. 

Preventive Maintenance 

Reasonable care in preventive maintenance will insure high 
reliability and long life for the transfer switch.  An annual 
preventive maintenance program is recommended. 

Yearly Inspection 

 

 

Hazardous voltage capable of causing shock, 
burns, or death is used in this transfer switch.  
Deenergize both Normal & Emergency power 
sources before performing inspections! 

Clean the enclosure.

  Deenergize all sources, then brush 

and vacuum away any excessive dust accumulation. Remove 
moisture with a clean cloth. 

Inspect the transfer switch contacts.

  Deenergize all 

sources, then remove the transfer switch barriers and check the 
contact condition.  The non-replaceable main contacts are 
designed to last the life of the transfer switch.  Reinstall the 
barriers carefully. 

Maintain transfer switch lubrication.

  Under normal 

operating conditions no further lubricating is required.  Renew 
factory lubrication if the transfer switch is subjected to severe 
dust, abnormal operating conditions, or if the TS coil(s) is 
replaced.  Order lubrication kit 75-100. 

Check all cable connections & retighten them.

  

Torque to values shown on the transfer switch label. 

Replacement Parts 

When ordering replacement parts provide the Serial No., Bill 
of Material No. (BOM), and Catalog No. from the transfer 
switch nameplate.  In the US call 800-800-2726 (ASCO) or 
contact  [email protected]

Manual Load Transfer 

This procedure will manually transfer the load if the controller 
is disconnected. 

 

 

Do not manually operate the transfer switch until 
both power sources are disconnected:  open both 
circuit breakers. 

1.

 

Deenergize both the normal and emergency source (open 
both circuit breakers). 

2.

 

Use the maintenance handle to manually operate the 
transfer switch to the opposite source.  See pages 3 and 4, 

Manual Operation

3.

 

Close the enclosure door.  If the transfer switch is in the 
emergency position, manually start the generator and then 
close the emergency source circuit breaker. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ASCO Services, Inc. (ASI) is ASCO Power 
Technologies’ national service organization.  
ASI can be contacted at 1-800-800-2726 for 
information on preventive maintenance agreements. 

Summary of Contents for 3ADTS

Page 1: ...URE COMMON ALARM NOT IN AUTO SIGNALING FEATURES INPHASE TRANSFER FEATURE FOR LOAD TRANSFER SOURCE AVAILABILITY SIGNALS EXTERNAL POWER SUPPLY COMPATIBILITY LOAD CURRENT METERING NON AUTOMATIC MANUAL OPERATION FOUR FUNCTION SOFTWARE BUNDLE REMOTE CONTROL FEATURES ...

Page 2: ...ASCO ASCO ...

Page 3: ...ASCO ...

Page 4: ...ASCO ...

Page 5: ...ASCO ...

Page 6: ...ASCO ...

Page 7: ...ASCO ...

Page 8: ...h for all mounting details including door opening space If bottom cable entry is used the foundation must be prepared so that the conduit stubs are located correctly Refer to the enclosure outline drawing for specified area and location Provide cable bending space and 1 inch minimum clearance to live metal parts When a concrete floor is poured use interlocking conduit spacer caps or a wood or meta...

Page 9: ...d with the transfer switch Be careful when stripping insulation from the cables avoid nicking or ringing the conductor Remove surface oxides from cables by cleaning with a wire brush When aluminum cable is used apply joint compound to conductors Tighten cable lugs to the torque specified on rating label Harnesses The transfer switch is connected to the left side of the controller by a plug in harn...

Page 10: ...s provided on the transfer switch for maintenance purposes only Manual operation of the transfer switch should be checked before it is energized operated electrically Do not manually operate the transfer switch until both power sources are disconnected open both circuit breakers 1 After deenergizing both power sources open the enclosure door Locate and remove the maintenance handle from the clip o...

Page 11: ...e positions ALL POWER MUST BE OFF Transfer Switch Position Interlocked Shafts Link between contact shafts prevents closing both N E contacts Maintenance Handle Shaft Indicators Normal E O upper contacts open N C lower contacts closed Load Disconnected E O upper contacts open N O lower contacts open Emergency E O upper contacts closed N C lower contacts open Note The hub and contact shaft turn in o...

Page 12: ...e settings in the controller 1 Close the normal source circuit breaker The normal source accepted and the load on normal lights should come on 2 Use an accurate voltmeter to check phase to phase and phase to neutral voltages present at the transfer switch normal source terminals 3 Close the emergency source circuit breaker Start generator if necessary The emergency source accepted light should com...

Page 13: ...s the transfer button The engine should start and run within 15 seconds For 3NTS 3NDTS the generator must be started manually at the generator The emergency source accepted light should come on 3 For 3ATS 3ADTS the transfer switch should transfer to the emergency position The load on emergency light should come on and the load on normal light should go off For 3NTS 3NDTS press the transfer button ...

Page 14: ...ns no further lubricating is required Renew factory lubrication if the transfer switch is subjected to severe dust abnormal operating conditions or if the TS coil s is replaced Order lubrication kit 75 100 Check all cable connections retighten them Torque to values shown on the transfer switch label Replacement Parts When ordering replacement parts provide the Serial No Bill of Material No BOM and...

Page 15: ...st 90 of nominal phase to phase voltage between transfer switch terminals EA and EC or EL1 and EL2 for 2 pole switches There are factory settings For 3ATS 3ADTS the transfer switch does not transfer the load to normal source when normal returns or after transfer test Wait for the feature 3A time delay For immediate retransfer press the transfer button bypass timer If inphase transfer is active wai...

Reviews: