4. commissioning
FIRST IGNITION OPERATION
1. Check the electrical
supply.
Complete
. . . . . . . . . . . . . . . .
Date
. . . . . . . . . . . . . . . . . . . . . . . . .
Installer
. . . . . . . . . . . . . . . . . . . . .
2. Check the type of gas
and change the gas if
necessary.
Complete
. . . . . . . . . . . . . . . .
3. Check the gas tightness.
Complete
. . . . . . . . . . . . . . . .
4. Measure the gas inlet
working pressure.
Complete
....................................................................
5. Check the fl ue system.
Complete
. . . . . . . . . . . . . . . .
6. Fill the system. See
section 4.1.2.
Complete
. . . . . . . . . . . . . . . .
7. Check the hydraulic water
tightness.
Complete
. . . . . . . . . . . . . . . .
8. Spin the pump.
Complete
. . . . . . . . . . . . . . . .
9. Purge the air by pressing
the Mode button for 5 sec.
Complete
. . . . . . . . . . . . . . . .
10. Set the heating power.
See section 4.5.1.
Complete
. . . . . . . . . . . . . . . .
11. Balance the central
heating circuit.
Complete
. . . . . . . . . . . . . . . .
12. Check operation in DHW
mode.
Complete
. . . . . . . . . . . . . . . .
13. Adjust DHW fl ow rate on
the boiler (if necessary).
Complete
. . . . . . . . . . . . . . . .
14. Check combustion rate
at maximum power. See
Section 4.5.
Complete
. . . . . . . . . . . . . . . .
16. Check the ionisation
current.
Complete
. . . . . . . . . . . . . . . .
15. Check combustion rate
at minimum power. See
Section 4.5.
Complete
. . . . . . . . . . . . . . . .
17. Explain the operation of
the boiler to the end user.
Complete
. . . . . . . . . . . . . . . .
18. Complete Benchmark
Checklist. See pages 58
& 59.
Complete
. . . . . . . . . . . . . . . .