12
Quick Start Guide: 7000 Series 1 RU-Gen 3 Data Center Switches
Four-Post Rack Mount
Chapter 3: Rack Mounting the Switch
3.2
Four-Post Rack Mount
The switch is mounted onto a four-post rack by assembling two rails onto the rear posts, sliding the
switch onto the rails, then securing the switch to the front posts.
The installation kit provides the following four-post mounting parts:
•
2 six-hole mounting brackets
•
2 rail-rods
•
2 rail-slides
The rail-rods and rail-slides assemble into two identical slide-rails.
Each chassis side has attachment pins that align with bracket holes. Pin orientation is symmetric and
equidistant, supporting bracket placements where the flange is flush with the front switch panel, flush
with the rear panel, or not flush with either panel. Each bracket hole includes a key-opening for placing
the bracket flush with the chassis and then locking it into place.
Important!
Attachment pins must engage at least five of the six bracket holes.
Goupilles de fixation doivent être lock au moins cinq des trous du six support.
Figure 3-5
displays proper bracket mount configuration examples.
Figure 3-6
displays an improper
bracket mount configuration example.
Figure 3-5: Bracket Mount Examples for Four-Post Rack Mount
Figure 3-6: Improper Bracket Mount Example for Four-Post Rack Mount
Front mount
Off-set mount
Rear mount