APV – Technische Produkte GmbH
Original operating manual LF 600 M1
Page 17
Requirements
The following requirements must be met for optimal fertilizer distribution:
•
The distributor must be installed horizontally on the implement in working position.
•
The pressure gauge must be installed where it can be checked from the driver's seat during
operation.
Required components, tools and materials
For this work step, the following components, tools and materials are required:
•
Distributor with bracket
•
Connecting hose
•
Pressure gauge with bracket
•
Nozzle holder
•
Nozzle
•
Hexagon key
Procedure for installation
To install the nozzles on the soil tillage implement or seeding units:
Step
Description
Explanation/illustration
1
Distribute the nozzles evenly across the entire working
width or on the seeding units of the implement.
2
Fasten the nozzle holder (plug connector) on the
implement.
3
Connect the hoses to the nozzle holder (plug connector),
see
Connecting the hoses
for more information (page 17).
4.3
Connecting the hoses
Purpose
The hoses carry the liquid fertilizer from the pump unit to the soil on the field. Before initial operation, all
hoses must be cut to an equal length between the distributor and the grooves and must be connected to
the nozzle holders.
For checking purposes, a pressure gauge is inserted in a hose between the distributor and nozzle holder
using a T-piece.
Requirements
The following requirement must be fulfilled for this work step:
•
None
Required components, tools and materials
For this work step, the following components, tools and materials are required:
•
Hose roll
•
Hose cutter