background image

-9-

the service switch).

c.

Switch off the branch circuit breaker.

Step 2 

- Remove electrical box cover.

Step 3

- Remove existing wire from boiler aquastat 

terminal C1 and connect to terminal #2 on 
DPDT relay.

Step 4

- Install wire from DPDT relay terminal #1 to boiler

aquastat terminal C1.

Step 5

- Connect terminals of 4 and 6 of DPDT relay "T-

T" terminals of boiler aquastat relay.

Step 6

- Connect BOILER MATE™ thermostat to L1, 

BOILER MATE™ and DPDT relay as shown 
in Schematic #4.

Step 7

- Connect L2 to BOILER MATE™ circulator 

and DPDT relay as shown in Schematic #4.

B.

Use only the heating system circulator.  

When wiring a separate, full-flow 3-way zone valve, follow
steps in 1B. above.

Note:

Priority comes from the valve operation and not the

wiring.

D. POST-INSTALLATION and 
START-UP CHECKLIST

After the BOILER MATE™ has been  plumbed and wired, it is now
ready to be set for automatic operation. Turn on the boiler and
safety switches.

TEMPERATURE ADJUSTMENT

PAINFUL SCALDING WITH POSSIBLE
SERIOUS AND PERMANENT INJURY

CAN OCCUR IF THE TEMPERATURE IS SET TOO HIGH OR
THE THERMOSTAT IS NOT FUNCTIONING PROPERLY.

The thermostat controls the maximum water temperature in the
BOILER MATE™. 

If set too high, the resulting hot water can

cause painful scalding with possible serious and permanent
injury.

The temperature at which this occurs varies with a

person’s age and the length of time in contact with the water.
The slower response time of infants, aged or handicapped
persons increases the hazard to them.

It is recommended that the temperature control be set for the

lowest temperature which satisfies your hot water needs. This will
also provide the lowest operating costs. 

In conjunction with a Consumer Product Safety Commission
recommendation, an initial setting of 120° F is recommended.
This may or may not be suitable for your needs. Check the
temperature at a hot water faucet soon after the burner has
completed the first heating.  Adjust as needed. Note that
adjusting to a lower setting will not have an immediate effect. The
stored hot water will first have to be used.  Additional checks of
the water temperature should follow completion of a cycle.
Further adjustments may be necessary as you use your BOILER
MATE™ and water piping system.

NOTE: VALVES FOR REDUCING POINT OF USE
TEMPERATURE BY MIXING COLD AND HOT WATER ARE
AVAILABLE.  CONSULT A LICENSED PLUMBER OR THE
LOCAL PLUMBING AUTHORITY.

SEPARATE CIRCULATOR

ZONE VALVES - SCHEMATIC 3

3-WIRE ZONE VALVES

4-WIRE ZONE VALVES

PRIORITY W/CIRCULATORS - SCHEMATIC 4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Summary of Contents for BOILER MATE TD-41Z

Page 1: ...follow the required procedures as you use your BOILER MATE Return this booklet to its original envelope and keep it with the BOILER MATE This manual may become out of date by later amendments Check ou...

Page 2: ...R CLOSED HYDRONIC HEATING SYSTEMS 4 INSTALLATION Forced Hot Water Closed Hydronic Heating System 6 A General Installation Requirements 6 B Piping 7 C Electrical Wiring 8 D Post Installation and Start...

Page 3: ...PLUMBING FIXTURE WILL NOT RESULT IN A DRY BOILER IF THE BOILER CONTINUES TO FIRE AN EXPLOSION HAZARD EXISTS THIS UNIT MUST BE INSTALLED AS A SEPARATE HEATING ZONE DO NOT CONNECT THIS UNIT TO AN EXISTI...

Page 4: ...at the same time the BOILER MATE may not be supplied with enough hot boiler water to recover adequately The delivery of domestic hot water will be diminished In many but not all cases this is not a pr...

Page 5: ...REQUIRED IF a Back flow preventer check valve or pressure reducing valve is installed anywhere between the BOILER MATE and the city main As needed pipe dope or Teflon tape Do not forget an EXTROL and...

Page 6: ...ble Surfaces LEFT SIDE 10 REAR 1 RIGHT SIDE 10 FLOOR 0 TOP 30 FRONT 1 Recommended Clearance for Servicing LEFT 10 HEAD ROOM 30 RIGHT 10 REAR 1 FRONT 30 4 Instructions for reversing unit The unit is de...

Page 7: ...TRANSFER MEDIUM MUST BE LIMITED TO A MAXIMUM OF 30 PSIG BY AN APPROVED SAFETY OR RELIEF VALVE ON YOUR BOILER THE TANK PRESSURE MUST BE LIMITED TO 150 PSIG MAXIMUM BY THE INSTALLATION OF A TEMPERATURE...

Page 8: ...ions and ordinances or in the absence of such codes the National Electrical Code ANSI NFPA No 70 latest edition The BOILER MATE thermostat can be used for either 24 or 120V AC The thermostat is packag...

Page 9: ...the BOILER MATE If set too high the resulting hot water can cause painful scalding with possible serious and permanent injury The temperature at which this occurs varies with a person s age and the le...

Page 10: ...10...

Page 11: ...valve from the top of the BOILER MATE taking care to avoid contact with the hot water which may drain out of the lines leading to the domestic uses 5 Drain the BOILER MATE until the water within the t...

Page 12: ...THE ABSENCE OF LOCAL CODES WITH THE NATIONAL ELECTRIC CODE 2 HEAT EXCHANGER PACKAGE INCLUDE ITEMS 5 11 3 TORQUE NUTS 12 TO 14 FT LBS FAILURE TO USE THE CORRECT REPLACEMENT PARTS MAY MAKE YOUR UNIT UNS...

Page 13: ...filter strainer in steam boiler systems 2 Insufficient or runs out of 1 BOILER MATE 1 Set BOILER MATE hot water at faucet temperature setting too low temperature control to a higher setting 2 Undersiz...

Page 14: ...14 DATE SERVICE PERFORMED COMMENTS CONTRACTOR 9 SERVICE RECORD...

Page 15: ...d as described in the Manual provided with the Product to any failure or malfunction resulting from abuse including freezing improper or negligent handling shipping by anyone other than AMTROL storage...

Page 16: ...West Warwick Rhode Island 02893 Part 9040 628 REV B 7 04 16...

Reviews: