19
DOWN CONTACTOR (M2)
a) Install a min 18AWG jumper between terminal 60 and 66. This will
apply 24Vdc directly on the M2 coil
b) Call for an lower landing, after 1.5 sec, the controller should code à fault
c) Reset the controller by pressing Z4 on the PLC
d) Call for a lower landing and press the CAB E-stop, Lift should stall
immediately.
e) Reset the controller by pressing Z4 on the PLC
f) Call for a lower landing and activate the upper safety flap the same way it
would hit an obstacle by moving downward.
g) Lift should stall and code à fault
h) Remove jumper between terminals 60 and 66.
i) Reset controller by pressing Z4 on the PLC
j) Remove wire from terminal 63
k) Call for an downward move , lift should stall after 0.5 sec, and code a
fault
l) Reset controller by pressing Z4 on the PLC
m)
Reconnect wire to terminal 63
n) Reset controller by pressing Z4 on the PLC
Summary of Contents for Titan Incline Lift
Page 1: ...INSTALLATION Titan Incline Lift ...
Page 8: ...9 UPPER MECHANICAL STOP ...
Page 11: ...12 INSPECTION Titan ...
Page 13: ...14 MANUAL MOVING OF THE PLATFORM ...
Page 20: ...21 MAINTENANCE Titan Incline ...
Page 23: ...24 USER MANUAL Titan Incline Lift ...
Page 25: ...26 RATING PLATE ...