35
Hurricane Tie Down Kit Installation Continued...
Tie down kits include 1
2’
anchor, 2 wire clamps and a minimum of
48”
wire cable. Cable lengths
will vary
depending on
the height of your system.
Be sure to view each kit so that you use the proper length of cable for each section.
Tie downs are to be installed UNDER the ramp section where there is enough clearance so the tie down does NOT inter-
fere with the under side of the ramp as it lays over it. Less than
12”
in height, you may relocate the tie down to one side
of the ramp and in the center of the section.
The tie down should be centered under the ramp. When securing the cable, you should choose a
“
RIB
”
under the ramp
and drill two(2)
1/4”
holes, one on each side of the CENTER of the ramp.
DO NOT drill through the side of the ramp.
Run your wire cable through the drilled holes and down to the top of the tie down anchor. Secure the cable with the two
(2) included clamps in your kit.
The cable
should be tight
, allowing about an
inch of slack
for slight movement.
Anchors should be in the ground with the top of the anchor just resting on the ground.
Any Questions, please contact your ramp supplier.
888
-
790
-
9269
We recommend the customer/contractor to call the local utilities to provide a free (miss dig) markings
to insure proper placement of anchors.
Allow for up to 10 days for your local miss dig company to come out.
5x5
5
TT
6
5x5
6
6
5x5
6