Ambirad VISION COMPACT Series Operation, Maintenance And Servicing Manual Download Page 13

11

Figure 20

Remove the screws securing the combustion
chamber cover.  Lift off thelid and gasket
checking the gasket for signs of splitting,
and replace on re-fit as required.

Figure 21

Figure 22

Figure 23

Figure 24

Using a screwdriver through the holes in the
burner head, slacken then unscrew the
burner head.

Slacken with a spanner, then unscrew the
injector from its carrier.  If servicing the
injector, blow through orifice, never drill or
broach out or use wire to clean.  Replace if
blocked.

Remove the screws securing the electrode
assembly to the side of the burner assembly.

Examine the electrode assembly and if in
not good condition replace as necessary by
removing the screws as indicated and 
disconnection of leads from wiring harness.

On service or replacement of the electrode
assembly check the spark electrode gap is
3.5mm = or -0.5mm.

Replace burner head and injector if 
necessary and re-fit components in reverse
order of removal.

Disconnect connectors on gas valve from
wiring harness and remove silicon tube.

Figure 25

Figure 26

Remove the four screws securing the gas
valve to the burner assembly.  The gas valve
can now be replaced.

After re-fitting in reverse order of removal,
and prior to fitting the controls cover,
ensure all joints are gas tight, and set burner
pressure to that indicated on the data
badge.

Vacuum switch

Remove the air grille or ducted air  
attachement from the side of the burner
assembly.

Electrode assembly

Gas valve

Follow instructions for replacment of burner
head and injector then proceed as follows:

Disconnect the two silicon rubber tubes and
the electrical connectors.

Figure 27

Remove the vacuum switch bracket screws
the unscrew pressure from the bracket.

Re-fitting in reverse order of removal, then
ensure connections are made as indicated in
the diagram below.

Burner head, Injector and Electrode
assembly

Summary of Contents for VISION COMPACT Series

Page 1: ...Operation maintenance and servicing manual VC12 VC20 GAS FIRED RADIANT TUBE HEATERS VISION COMPACT...

Page 2: ...f Vision Compact heaters Flue connection Fresh air ducted inlet all models Commissioning for individually flued and unflued heaters Routine service Herringbone adjustment Replacement of components Tro...

Page 3: ...lations 1998 Due account should also be taken of any obligations arising from the Health and Safety at Works etc Act 1974 In addition the installation must be carried out in accordance with the curren...

Page 4: ...ded by the institute of Gas Engineers the manufacturer and Ambi Rad Ltd These instructions must be carried out in accordance with the relevant provisions of the gas safety installation and use regulat...

Page 5: ...leaflets Circuits and controls All such controls and switchgear must be rated to handle the total inductive load of the circuit they control Load per Ambi Rad heater is 0 55 amp For large installatio...

Page 6: ...ade to good sound engineering practice or of a proprietary type fixing They must be adequately fixed and designed to carry the whole weight of the heater In the event of suitable roof steelwork not be...

Page 7: ...n installing the heater at an angle the combustion fan outlet should be positioned so that it remains vertical It is recommended that sufficient clearance from any fixed structure e g a wall is given...

Page 8: ...e in operation carry out a flow visualisation check using a smoke producing device e g smoker match puffer or joss stick The device shall produce an even trace so that the flow can be observed and the...

Page 9: ...and resistance to earth To shut down the heater switch off the power supply to the heater Automatic control of the heater or a series of heaters may be achieved by incorporating thermostats time switc...

Page 10: ...tions but in exceptional dusty or polluted conditions more frequent servicing may be required The manufacturer offers a maintenance service Details are available on request Tools required for servicin...

Page 11: ...country that the appliance is installed For servicing of injector electrode assembly refer to Section 14 Figure 11 Figure 12 Figure 13 Figure 14 Figure 15 Remove the 2 M6 bolts and 2 M5 screws securi...

Page 12: ...d pipe at the gas valve Figure 18 Figure 19 Remove the fixing screws securing the controls cover to the burner assembky and the side of the product Remove the controls cover Slide the burner assembly...

Page 13: ...is 3 5mm or 0 5mm Replace burner head and injector if necessary and re fit components in reverse order of removal Disconnect connectors on gas valve from wiring harness and remove silicon tube Figure...

Page 14: ...e wiring harness and the ignition high tension lead Remove the plastic push clips and replace the controller Re fit in reverse order of removal ensuring electrical connections are made Figure 29 S I T...

Page 15: ...nd 7 of burner control unit plug A reading of 10 000 ohms indicates short circuit on gas valve burner indicator light or associated wiring HB Herringbone system only Leaks in joint separation in manif...

Page 16: ...mbly 200191 Pressure switch SIT or EAC M101355 VC20 Natural gas G20 only 3 8mm injector 2290 Burner orifice plate 200520 Burner support spinning 200568 SUB VC20 Propane G31 only 2 3mm injector 2281 2...

Page 17: ...actual or proposed flue measured from the flue spigot 7 7 other resistances of actual flue terminal 1 0 6 0 25 90 bend 0 0 0 135 bend 0 0 0 flue pipe 5 46 1 75 6 06 2 He 2 50 6 22 Note 1m of actual fl...

Page 18: ...Figure 30 Example layout of a typical flue arrangement Example Layout Of A Typical Flue Arrangement GCI Terminal Heater 1 0 m min 7 0 m max Spigot 16...

Page 19: ...occurs again switch off heater and call out a service engineer Note U bend will glow but this is acceptable To switch off Vision Compact heater 1 Switch off electrical supply to the heater The burner...

Reviews: