108
Then start up the platform and check if the buzzer and the maximum inclination indicator light (see
figure below) are working
Maximum inclination indicator light
Try to lift the basket and check, once the maximum transport height is reached (floor surface < 2000
mm), if the platform gets locked and prevents any lifting manoeuvre. Perform the test in the 2
directions.
CHECK WITH 1° OF LATERAL INCLINATION
Prepare the platform for use with stabilizers, then place it on a STABLE plane inclined >1° with respect
to the horizontal, in the following configuration (inclination reached >1°).
Then start the platform, enable the stabilizers until they are completely out and the maximum transport
height is reached (floor surface <
2000 mm)
. Check if the buzzer and the maximum inclination indicator
light (see figure below) are working.
Maximum inclination indicator light
Try to lift the basket and ensure the safety system prevents the lifting manoeuvre. Perform the test in
the 2 directions.
Summary of Contents for BiBi 850 HE
Page 6: ...5 Chapter 1 General information...
Page 10: ...9 1 6 Performances H I A B L F E C G...
Page 19: ...18 Chapter 2 Safety information...
Page 24: ...23...
Page 25: ...24 2 3 2 Warning command danger identification and instruction signs...
Page 40: ...39 Chapter 3 Machine Description...
Page 41: ...40 3 1 Structure of the machine 2 4 5 6 7 9 10 11 13 14 19 27 28 15 18...
Page 42: ...41 View from A 20 22 21 23 24...
Page 43: ...42 12 8 25 16...
Page 44: ...43 17 2 26...
Page 45: ...44 3...
Page 56: ...55...
Page 59: ...58 Chapter 4 Instructions for use...
Page 68: ...67...
Page 69: ...68 For more information refer to Engine Use maintenance manual...
Page 71: ...70...
Page 72: ...71 For more information refer to Engine Use maintenance manual...
Page 91: ...90 Chapter 5 Emergency procedures...
Page 94: ...93 Chapter 6 Maintenance...
Page 105: ...104 Electrical panel casing Battery 1...
Page 116: ...115...
Page 117: ...116...
Page 118: ...117...
Page 119: ...118...
Page 120: ...119...
Page 123: ...122...
Page 124: ...123...
Page 125: ...124...
Page 133: ...132...
Page 136: ...135 HATZ ENGINE...
Page 137: ...136...
Page 138: ...137...
Page 139: ...138 Chapter 7 Demolition...
Page 141: ...140 APPENDICES...
Page 142: ...141 Appendix 1 Declaration of conformity...
Page 144: ...143 MANDATORY ROUTINE INSPECTIONS Date Observations Seal Signature...
Page 157: ...156 Appendix 4 Hydraulic diagram Appendix 5 Circuit diagram...