background image

4

GATE SYSTEM DESIGN AND INSTALLATION 

SAFETY CHECK LIST: 

x

The LP1000 operator may be installed on a Class I, II, III, or 
IV Vehicular Slide Gate.  See page 3 for an explanation of the 
different Class locations.  See the last page of this manual for 
the operator specifications (voltage, maximum gate weight & 
length etc.). 

x

Make sure that the gate moves freely, all rollers are in good 
working order, the gate does not bind in any manner and the 
gate area is clean and free of irregularities.  DO NOT 
INSTALL THE OPERATOR UNTIL ALL GATE 
PROBLEMS HAVE BEEN CORRECTED. 

x

Do not increase the built-in overload detector adjustment to 
compensate for a poorly working gate.  A well maintained gate 
will ensure easy manual operation (if needed) and maximum 
operator obstruction sensitivity. 

x

Install  the operator on the inside of the property/fence line.  
DO NOT install an operator on the public side of the fence line 
or gate. 

x

Make sure the gate operating system is placed far enough back 
from the road to eliminate traffic backup.  The distance from 
the road, size of the gate, usage level and gate cycle/speed must 
be taken into consideration to eliminate potential hazards. 

x

The gate must be installed in a location so that enough 
clearance is supplied between the gate and any adjacent 
structures when opening and closing to reduce the risk of 
entrapment.  

x

For ORNAMENTAL “GRILL TYPE” GATES (or any other 
type of open gate where a handhold or toehold may be 
achieved), injuries may occur when people put arms through 
the openings or children “ride” the gate by standing on the bars 
and holding on to the gate.  THIS POTENTIAL HAZARD 
CAN BE MINIMIZED BY INSTALLING A MESH SCREEN 
ON THE GATE.  Allstar strongly recommends the entire gate 
and adjacent fence area the gate covers when open be meshed 
or guarded such that a handhold or toehold cannot be achieved.  
At a minimum all openings on a horizontal slide gate must be 
guarded or screened from the bottom of the gate to a minimum 
of 4 feet above the ground to prevent a 2-1/4 inch (57.15 mm) 
sphere from passing through the openings anywhere in the 
gate, and in that portion of the fence the gate covers when in 
the open position.  See Figure 2. 

x

All Allstar gate operators are VEHICULAR GATE 
OPERATORS and as such are NOT RECOMMENDED FOR 
PEDESTRIAN traffic.  In installations where pedestrians are 
likely to be nearby,  install a pedestrian gate and use leading 
edge detectors and/or photocells in your design to protect 
system entrapment zones.  Allstar can provide these products 
for incorporation in your design. 

x

Use the illustration at left (Figure 3) to minimize the risk of 
injury in your design of the swing gate operator system.  
IDENTIFY THE ENTRAPMENT ZONES AND PINCH 
POINT AREAS IN YOUR GATE.  Design the gate 
installation to minimize the risk of entrapment in these areas.  
Install additional safety equipment such as four wire edges and 
photocells to further minimize risk.  All entrapment zones are 
required to be protected. 

x

Entrapment Zones:

  Design in personal entrapment 

protection devices to protect people from entrapment in the 
zones shown in Figure 3 at left.  Install vertical posts with gate 
edges attached on both sides of the gate to prevent body 
entrapment.

TO REDUCE THE RISK OF SEVERE 

INJURY OR DEATH: READ AND FOLLOW 

ALL INSTALLATION INSTRUCTIONS AND 

GATE SYSTEM DESIGN PARAMETERS!

WARNING! 

 A

: GATE SYSTEM DESIGN / INSTALLATION 

Figure 3 

106709 

Figure 2 

104949 

Summary of Contents for LEADER PLUS LP1000

Page 1: ...rements for Vehicular gate operators LEADER PLUS Model LP1000 Heavy Duty Vehicular Slide Gate Operator READ THIS MANUAL CAREFULLY BEFORE INSTALLATION OR USE SAVE THESE INSTRUCTIONS 107063 Serial Date...

Page 2: ...there to protect you and your equipment Pay close attention to these boxes as you follow the manual WARNING Indicates a MECHANICAL hazard of INJURY OR DEATH Gives instructions to avoid the hazard CAU...

Page 3: ...TE TESTED ON THE LOG LOCATED ON PAGE 2 OF THIS MANUAL See Figure 1 pg 2 Connections for External Entrapment Prevention Sensors Because all gate system installations are different the LP1000 control pa...

Page 4: ...IAL HAZARD CAN BE MINIMIZED BY INSTALLING A MESH SCREEN ON THE GATE Allstar strongly recommends the entire gate and adjacent fence area the gate covers when open be meshed or guarded such that a handh...

Page 5: ...be exposed EVEN IF THE RED POWER LIGHT IS NOT LIGHTED HIGH VOLTAGE AC MAY STILL BE PRESENT ON TERMINALS L1 AND L2 NEVER LEAVE THE INSTALLATION WITH THE CONTROL BOX COVER REMOVED x ALWAYS TURN OFF THE...

Page 6: ...tor The bolt pattern for the LP1000 is 12 3 16 wide by 12 1 4 long The two rear bolts closest to the gate should be no closer than 5 1 2 from the near side of the gate to allow sufficient clearance fo...

Page 7: ...ol wires MUST NEVER be routed in the same conduit as A C power wires Always consult and follow all local electrical codes 106728 Figure 8 Chain Configuration Normal Drive Figure 7 Service Conduits 106...

Page 8: ...d in wires need not be in PVC but must have at least six 6 twists per running foot For a saw cut installation observe the method recommended in Figurez10 for the corners When installing a two loop rev...

Page 9: ...with the operator in place Before inserting the remaining redhead bolts make sure the operator is sitting level If any corners of the operator are resting above the pad slide flat washers under the op...

Page 10: ...100 OHMS resistance and for more than 100 milliseconds duration Two of the inputs ALTERNATE and RADIO OPEN are momentary inputs where the signal must be released and re entered to be recognized The r...

Page 11: ...parate from the receiver s output connection This is necessary as the LP1000 control board 24 VAC is isolated from chassis ground A 3 prong receiver CANNOT be installed in association with the LP1000...

Page 12: ...factory configured for right hand installations If it is installed in a left hand installation make sure the main power switch is off and locate the 8 pin motor wire connector in the upper center of t...

Page 13: ...limit nut two more slots to give the operator time to stop the gate after the limit switch has been activated Release the detent plate and make sure it drops into the slots on both limit nuts Manually...

Page 14: ...he test mode the operator control board changes to a sleep mode and a low pulsed tone is heard from the audible output You can reset the operator for a renewed 20 test cycles by turning the power off...

Page 15: ...rol board of the LP1000 operator See Figure 22 These lights are used to verify proper operation of the LP1000 TURN ON THE MAIN POWER SWITCH Remove the white high voltage connector from the control boa...

Page 16: ...lots in either direction to fine tune the gate s limits of travel When final adjustment has been completed insure that the detent plate is firmly seated in the slots Review Figure 18 Page 13 SETTING T...

Page 17: ...operator should respond to an obstruction not encountered by the other the gates will temporarily get out of sync Synchronization will be restored after the next input command cycle D STARTING THE OPE...

Page 18: ...to terminals 3 or 13 COMMON Multiple devices may be connected in parallel NAME DESCRIPTION 12 OPEN EDGE Momentary or continuous signal This input is active only when referenced to the opening directi...

Page 19: ...19 D STARTING THE OPERATOR Figure 23 Wiring Schematic and Diagram 110146...

Page 20: ...or Close Contact Sensor input or a Close Overload activation will cause the gate to stop pause and reverse for approximately 2 inches in the Open direction xIf the gate is moving in a Close direction...

Page 21: ...ollowing safety features x Electric gate edges x Enclosed tracks x Vertical guard posts x Protective screen mesh x Photoelectric sensors x Instructional and precautionary signs x Covers for exposed ro...

Page 22: ...mpensate for a poorly operating slide gate Correct all mechanical problems on the gate and gate hardware before installing the gate operator Have a qualified service technician make repairs to the gat...

Page 23: ...r 2 EA not shown 110136 Installation Owner s Manual 1 EA 24b 111886 Box Cover 4 x 2 Duplex Raised 1 EA OPERATOR EXPLODED VIEW 110153 OPERATOR PARTS LIST RISK OF ELECTROCUTION TURN OFF THE MAIN POWER S...

Page 24: ...purchase for multi family and commercial use To obtain service contact your dealer To obtain service under this warranty the buyer must obtain authorization instructions for the return of any goods f...

Reviews: