The limit switches are now roughly adjusted.  If the gate should stop 
short of fully opened or closed, or if it bangs against the end stops 
during operation, the limit switches can be fine-tuned after the operator 
is powered up.  (See FINAL SETTING OF THE LIMIT SWITCHES, P. 
16.) 

SETTING THE LIMIT SWITCHES 

Before turning on the main power, set the limit switches which are 
located on top of the frame, between the control box and the reducer 
gearbox. See Figure 18.  In a right-hand installation, the switch nearest 
the control box is the open limit switch.  In a left-hand installation, the 
switch closest to the gearbox is the open limit switch.   

Manually push the gate all the way open.  Press down on the spring 
loaded detent plate and rotate the open limit nut toward the open limit 
switch contactor until you hear the open limit switch click.  Rotate the 
limit nut two more slots to give the operator time to stop the gate after 
the limit switch has been activated.  Release the detent plate and make 
sure it drops into the slots on both limit nuts. 

Manually push the gate all the way closed.  Depress the detent plate and 
rotate the close limit nut clockwise until the close limit switch clicks.  
Again rotate the close limit nut two more slots.  Release the detent plate 
and make sure both limit nuts are firmly seated. 

D: STARTING THE OPERATOR  

THE MOTOR WIRE CONNECTOR AND THE LIMIT 

HARNESS CONNECTOR MUST BOTH ALWAYS BE IN 

EITHER THE RIGHT OR LEFT POSITIONS.  IF ONE IS 

IN THE RIGHT POSITION AND THE OTHER IN THE 

LEFT POSITION, THE OPERATOR WILL NOT STOP 

THE GATE WHEN IT REACHES THE END OF TRAVEL. 

           W A R N I N G !  

 Detent  Plate 

Limit Switch “Open” - LH 
Installation (“Closed” RH) 

Limit Switch “Closed” - LH 
Installation (“Open” RH) 

Limit Nuts 

107031 

Control Box 

Figure 18:  Setting the Limits 

LOCATION OF 

RIGHT-HAND &

HIGH VOLTAGE

LIMITS

LEFT HAND

CONNECTIONS

HARNESS

Figure 17: Control Board Settings for LH/RH Operation 

110134 

Summary of Contents for LEADER PLUS LP1000

Page 1: ...rements for Vehicular gate operators LEADER PLUS Model LP1000 Heavy Duty Vehicular Slide Gate Operator READ THIS MANUAL CAREFULLY BEFORE INSTALLATION OR USE SAVE THESE INSTRUCTIONS 107063 Serial Date...

Page 2: ...there to protect you and your equipment Pay close attention to these boxes as you follow the manual WARNING Indicates a MECHANICAL hazard of INJURY OR DEATH Gives instructions to avoid the hazard CAU...

Page 3: ...TE TESTED ON THE LOG LOCATED ON PAGE 2 OF THIS MANUAL See Figure 1 pg 2 Connections for External Entrapment Prevention Sensors Because all gate system installations are different the LP1000 control pa...

Page 4: ...IAL HAZARD CAN BE MINIMIZED BY INSTALLING A MESH SCREEN ON THE GATE Allstar strongly recommends the entire gate and adjacent fence area the gate covers when open be meshed or guarded such that a handh...

Page 5: ...be exposed EVEN IF THE RED POWER LIGHT IS NOT LIGHTED HIGH VOLTAGE AC MAY STILL BE PRESENT ON TERMINALS L1 AND L2 NEVER LEAVE THE INSTALLATION WITH THE CONTROL BOX COVER REMOVED x ALWAYS TURN OFF THE...

Page 6: ...tor The bolt pattern for the LP1000 is 12 3 16 wide by 12 1 4 long The two rear bolts closest to the gate should be no closer than 5 1 2 from the near side of the gate to allow sufficient clearance fo...

Page 7: ...ol wires MUST NEVER be routed in the same conduit as A C power wires Always consult and follow all local electrical codes 106728 Figure 8 Chain Configuration Normal Drive Figure 7 Service Conduits 106...

Page 8: ...d in wires need not be in PVC but must have at least six 6 twists per running foot For a saw cut installation observe the method recommended in Figurez10 for the corners When installing a two loop rev...

Page 9: ...with the operator in place Before inserting the remaining redhead bolts make sure the operator is sitting level If any corners of the operator are resting above the pad slide flat washers under the op...

Page 10: ...100 OHMS resistance and for more than 100 milliseconds duration Two of the inputs ALTERNATE and RADIO OPEN are momentary inputs where the signal must be released and re entered to be recognized The r...

Page 11: ...parate from the receiver s output connection This is necessary as the LP1000 control board 24 VAC is isolated from chassis ground A 3 prong receiver CANNOT be installed in association with the LP1000...

Page 12: ...factory configured for right hand installations If it is installed in a left hand installation make sure the main power switch is off and locate the 8 pin motor wire connector in the upper center of t...

Page 13: ...limit nut two more slots to give the operator time to stop the gate after the limit switch has been activated Release the detent plate and make sure it drops into the slots on both limit nuts Manually...

Page 14: ...he test mode the operator control board changes to a sleep mode and a low pulsed tone is heard from the audible output You can reset the operator for a renewed 20 test cycles by turning the power off...

Page 15: ...rol board of the LP1000 operator See Figure 22 These lights are used to verify proper operation of the LP1000 TURN ON THE MAIN POWER SWITCH Remove the white high voltage connector from the control boa...

Page 16: ...lots in either direction to fine tune the gate s limits of travel When final adjustment has been completed insure that the detent plate is firmly seated in the slots Review Figure 18 Page 13 SETTING T...

Page 17: ...operator should respond to an obstruction not encountered by the other the gates will temporarily get out of sync Synchronization will be restored after the next input command cycle D STARTING THE OPE...

Page 18: ...to terminals 3 or 13 COMMON Multiple devices may be connected in parallel NAME DESCRIPTION 12 OPEN EDGE Momentary or continuous signal This input is active only when referenced to the opening directi...

Page 19: ...19 D STARTING THE OPERATOR Figure 23 Wiring Schematic and Diagram 110146...

Page 20: ...or Close Contact Sensor input or a Close Overload activation will cause the gate to stop pause and reverse for approximately 2 inches in the Open direction xIf the gate is moving in a Close direction...

Page 21: ...ollowing safety features x Electric gate edges x Enclosed tracks x Vertical guard posts x Protective screen mesh x Photoelectric sensors x Instructional and precautionary signs x Covers for exposed ro...

Page 22: ...mpensate for a poorly operating slide gate Correct all mechanical problems on the gate and gate hardware before installing the gate operator Have a qualified service technician make repairs to the gat...

Page 23: ...r 2 EA not shown 110136 Installation Owner s Manual 1 EA 24b 111886 Box Cover 4 x 2 Duplex Raised 1 EA OPERATOR EXPLODED VIEW 110153 OPERATOR PARTS LIST RISK OF ELECTROCUTION TURN OFF THE MAIN POWER S...

Page 24: ...purchase for multi family and commercial use To obtain service contact your dealer To obtain service under this warranty the buyer must obtain authorization instructions for the return of any goods f...

Reviews: