Allied Construction Products, LLC www.alliedcp.com
SOM576701_14jan
34
12.0 N
2
Gas Charge Kit – [cont’d]
3. SLOWLY open valve on nitrogen bottle.
4. Adjust pressure regulator and SLOWLY fill the
accumulator.
5. Adjust the regulator to + 50 psi above the value
specified in the Technical Data Section.
NOTE:
Gas pressure is sensitive to temperature
changes. The technical data section lists the charge
pressure with the ambient temperature of 70
.
6. Wait 15 to 30 minutes for temperature of gas
inside accumulator to stabilize.
7. Recheck the gas pressure and make final
adjustments as necessary.
12.6 Remove the Charge Valve
1. Close charge bolt hand tight.
2. Close valve at nitrogen bottle.
3. Open bleed valve.
4. Remove charge valve, adapter and socket bolt
from accumulator.
5. Tighten charge bolt with torque wrench to 15 lb-ft
[20 Nm].
6. Check for leaks by filling the area surrounding the
charge bolt with clean hydraulic oil.
7. If no gas bubbles are observed, clean out oil and
re-install protective plug
8. Store nitrogen tank according to regulations
9. Store charge valve in protective case
Summary of Contents for AR110C
Page 60: ...SOM576701_14jan R ...