Chapter 7: Installing GS970EMX/20 and GS970EMX/28 Switches on a Wall
90
Installing the
Switch on a
Plywood Base
This procedure assumes that the plywood base for the switch is already
installed on the wall. Review “Reviewing Safety Precautions” on page 40
and “Choosing a Site for the Switch” on page 44 before performing the
procedure. Allied Telesis recommends a minimum of two people for this
procedure.
Warning
The device is heavy. Always ask for assistance before moving or
lifting it to avoid injuring yourself or damaging the equipment.
Warning
The device should be installed on the wall by a qualified building
contractor. Serious injury to yourself or others or damage to the
equipment may result if it is improperly fastened to the wall.
E105
To install the switch, perform the following procedure:
1. Place the switch on a table.
Note
If the bumper feet are attached to the bottom on the switch, remove
them before continuing.
2. Unpack the BRKT-J24 kit and verify the contents. Refer to Figure 22
3. Attach the four BRKT-J24 wall brackets to the sides of the switch, with
the sixteen M4x6mm screws included in the kit. Refer to Figure 53.
Figure 53. Attaching the BRKT-J24 Wall Brackets to the GS970EMX
Switch
Summary of Contents for CentreCOM GS970EMX Series
Page 6: ...6...
Page 12: ...Tables 12...
Page 16: ...Preface 16...
Page 56: ...Chapter 2 Beginning the Installation 56...
Page 70: ...Chapter 4 Installing the GS970EMX 20 Switch in an Equipment Rack 70...
Page 104: ...Chapter 8 Verifying the Switch 104...
Page 116: ...Chapter 10 Troubleshooting 116...