SECTION 2
OPERATIONS
050362
Page 40
To string line your screed, there are a few im-
portant steps that need to be followed.
• Place screed ends on a 2 x 6 or other wooden
type support.
• At approximately 1” out from the leading
edge of the screed blade, drive a nail into the
wooden support. NOTE: Nail should be on the
outside of the wooden support.
• Stretch a line as tight as possible from nail to
nail. Make sure that the nail is contacting each
support at the pint of blade contact.
• NOTE: The supports do not have to be on the
same level.
•
Use a short, flat piece of metal or wood as a
gauge block to compare the string to the bot-
tom surface of the screed blade and bull-float
blade.
• The blades should be equal to each other at
each splice. If they are not even, loosen jam
nuts and tighten top pipe coupler as described
on page 33.
String Lining
Summary of Contents for SSE12
Page 1: ...OPERATIONS PARTS MANUAL SSE12 SCREED Manual Part 064633 I REVISION B ...
Page 17: ...SECTION 1 SAFETY 050362 Page 17 SECTION 1 SAFETY ...
Page 18: ...SECTION 1 SAFETY 050362 Page 18 State Regulations Proposition 65 Warning ...
Page 19: ...SECTION 1 SAFETY 050362 Page 19 Federal Regulation Respiratory Hazard ...
Page 30: ...SECTION 1 SAFETY 050362 Page 30 Notes ...
Page 31: ...SECTION 2 OPERATIONS 050362 Page 31 SECTION 2 OPERATIONS ...
Page 41: ...SECTION 3 SERVICE 050362 Page 41 SECTION 3 SERVICE ...
Page 43: ...SECTION 4 PARTS 050362 Page 43 SECTION 4 Parts ...
Page 70: ...SECTION 4 PARTS 050362 Page 70 4 13 End Mount Engine Assembly Illustration ...