INSTALLATION GUIDELINES
10
of
38
www.alfalaval.com
4.0.0
Installation and Commissioning Guidelines
For details on Dimensions, Connections, Service area, etc.: See the order specific
dimension drawing.
The CIP unit is delivered as complete machine ready to bring into service.
Check and assemble the hoses carefully between CIP-unit and heat exchanger.
Please make sure the CIP module is in horizontal direction.
All electrical installations must be done in accordance with local regulations. A
certified electrician should carry out this job.
During working on the electrical installations, the main power supply must be shut off
at all times.
WARNING
Before start up please connect supply cable from customer to the socket located
on pump and heater trolley.
4.1.0
Unpacking
When unpacking, take care not to damage the CIP unit.
Check the delivery. Make sure that the CIP-unit with accessories is complete
according to packing list and orders.
Check the tank. The inlets and the outlets must be free from possible packing
materials.
Verify all electrical connections are intact.
Make sure that the CIP unit has not been damaged during the transport.
If transport damages are found, please contact local Alfa Laval agent.
Alfa Laval cannot be responsible for incorrect unpacking & handling of CIP unit.