INSTALLATION GUIDELINES
13
of
38
www.alfalaval.com
4.3.0 Electrical Installation
All electrical installations must be done in accordance with local regulations. A
professional electrician should carry out this job.
Apart from the fact that the electrical installation must be effected in a safe, proper
and approved way, the different methods of how to regulate the equipment should be
considered.
Please refer to ‘Start-up preparation’ in the below sections and decide how to adapt
the electrical installation to the means of operating the machinery.
During working on the electrical installations, the main power supply must be shut off
at all times.
The power supply is in accordance with the technical data for the unit. (see the
type tag on the motor and heater)
That electrical hooks-up are connected correctly
WARNING
Failure to comply with electrical regulations can cause risk of death by touching
electrified parts
4.4.0
Commissioning Instruction
1
The system must be commissioned before putting into operation.
It is the responsibility of customer or of by the customer appointed
responsible for the commissioning, to ensure that any person involved with
the commissioning and operation of this system is sufficiently skilled, has the
appropriate experience or has received adequate training.
Operators must read and understand the
“Commissioning Instructions”,
“System Operating Instructions”, and the Operating Instructions of the
respective equipment before start-up of the system.
Before start up please connect supply cable from customer to the socket
located on pump and heater trolley.