background image

 

Aktobis AG, Borsigstr. 20, D-63110 Rodgau / Germany 

www.AKTOBIS.de

 

Email: [email protected] 

 
 

17. marking 

The equipment must be marked to indicate that it has been taken out of service and that the 
refrigerant has been drained. The marking must be dated and signed. Ensure that there are 
markings on the equipment stating that the equipment contains flammable refrigerant. 
 

18. reprocessing 

When removing refrigerant from a system, either for maintenance or decommissioning, it is 
recommended standard practice that all refrigerants are safely removed. When transferring 
refrigerant into cylinders, ensure that only suitable refrigerant recovery cylinders are used for 
this purpose. Ensure that the correct number of cylinders are available to hold the total amount 
of refrigerant. All cylinders used must be suitable and labelled for the refrigerant being 
reprocessed (i.e. special cylinders for reprocessing refrigerant). The cylinders must have a 
pressure relief valve and a connected shut-off valve and be in good working order. Empty 
reprocessing cylinders shall be drained of air and, if possible, cooled before reprocessing. 
The reprocessing plant shall be in good working order with appropriate instructions concerning 
the respective equipment and shall be suitable for the reprocessing of flammable refrigerants. In 
addition, a set of calibrated scales in good working order must be available. Hoses must be 
complete with leak-free and proper disconnect couplings. Before using the recovery unit, check 
that it is in good working order, that it has been properly maintained and that all associated 
electrical components are sealed to prevent ignition in the event of a refrigerant release. If in 
doubt, contact the manufacturer. 
The reprocessed refrigerant must be returned to the refrigerant supplier in the correct 
reprocessing cylinder and the appropriate disposal certificate must be arranged. Do not mix 
refrigerants in remanufacturing units and especially not in cylinders. 
If a compressor or compressor oils are to be removed, ensure that they have been evacuated to 
an acceptable level to ensure that no flammable refrigerant remains in the lubricant. The 
evacuation process must be carried out before returning the compressor to the suppliers. Only 
electrical heating of the compressor housing may be carried out to speed up this process. When 
draining oil from a system, this must be done in a safe manner. 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Summary of Contents for WDH-930EEW

Page 1: ...ransport can sometimes occur despite careful instructions on the carton Therefore we ask you to let it stand upright for at least4 hours before using it for the first time so that the refrigerant in t...

Page 2: ...and in the worst case to overheating and or fire Make sure that no moisture gets to the electrics of the unit Only use the recommended voltage for operating the unit Make sure that the power cable is...

Page 3: ...es heat Please note that the refrigerant is odourless and therefore a leak cannot be detected immediately by an emerging odour If refrigerant leaks it may ignite or explode especially in poorly ventil...

Page 4: ...trolled procedure to minimise the risk of flammable gases or vapours being present during the execution of the work 2 general work area All maintenance personnel and other persons in the vicinity must...

Page 5: ...t and the ventilation outlets are running properly and are not blocked 8 testing of the electrical equipment Before repairing and maintaining electrical components preliminary safety checks and inspec...

Page 6: ...re considered acceptable for systems containing flammable refrigerants Electronic leak detectors must be used to detect flammable refrigerants but their sensitivity may not be sufficient or they may n...

Page 7: ...filling but before commissioning A verification leakage test must be carried out before leaving the site 16 decommissioning Before performing this procedure it is necessary for the technician to be fu...

Page 8: ...reprocessing The reprocessing plant shall be in good working order with appropriate instructions concerning the respective equipment and shall be suitable for the reprocessing of flammable refrigerant...

Page 9: ...r 20 D 63110 Rodgau Germany www AKTOBIS de Email info aktobis de Description of the unit parts Air filter Castors Condensation tank Carrying handle Air intake Control panel Blower Output Connection po...

Page 10: ...back in place and wait approx 30 minutes so that the internal coolant can settle again 1 2 Insert the mains plug properly into the socket 1 3 Check that the condensation tank is properly seated in th...

Page 11: ...itches to standby mode and the signal light stops flashing To reactivate the WLAN function switch off the unit and then press and hold the On Off button for 5 seconds until you hear a tone confirming...

Page 12: ...orsigstr 20 D 63110 Rodgau Germany www AKTOBIS de Email info aktobis de 3 6 Proper drainage of condensation water with hose connection Make sure that the hose always has a slight slope see the followi...

Page 13: ...liance This is dangerous 5 Cleaning 5 1 Cleaning the housing a Please disconnect the mains plug before cleaning the construction dryer b Only use mild cleaning agents to clean your construction dryer...

Page 14: ...ay from walls and ceilings because otherwise the humidity value determined for the room air will be falsified As with all building dryers the dehumidification performance is decisively influenced by t...

Page 15: ...mpletely or partially dismantled units Conformity The construction dryer has been tested and itself and or parts thereof have been manufactured under the following safety standards T V Rheinland GS te...

Page 16: ...____________________________ _________________________________________________________ _________________________________________________________ _______________________________________________________...

Reviews: