A Connect the drain pipe

● Water condensation must be evacuated directly to the outside; observe an appropriate slope for the evacuation duct, which should slopedownwards the 

case of a connection to the wastewater system (2.5 cm/m slope).

● An S-bend must be installed on the evacuation duct, below the level of the recovery tray of the unit.

● Provide insulation for the evacuation piping in the case of a risk of freezing or condensation.

● Evacuation with pump kit: (refer to instructions provided with kit).

  a.The unit is supplied with an evacuation piping.

  b.The right and left outlets are blocked off by a plug. Do not forget to remove this plug before connecting the evacuation piping.

● In the case of a ceiling mounted installation, run the evacuation piping down along the side panel and secure it with clamps as shown below. Also break 

the preformed cut-out in the coner of the intake grid.

Condensate recovery 

tray

Evacuation 

tube

Gas tube

7

ELECTrICAL WIrING CONNECTION

Tightening torque for the terminal screws
Use the correct screwdriver for tightening the terminal 

screws. If the blade of screwdriver is too small, the head 

of the screw might be damaged, and the screw will not be 

properly tightened. If the terminal screws are tightened 

too hard, screws might be damage. Refer to the table 

right for the tightening torque of the terminal screws.

Terminal

Size

Tightening torque

Terminal block

M3.5

0.8~1.0N.m

5

 drAINAGE pIpE CONNECTION

Fig 14

Fig 15

Fig 16

Fig 17

Liquid 

tube

B Drainage test

   

Pour a glass of water into the drain tray-styrofoam,ensure that water flows out from drain hose 

    of the indoor unit,a long of 1 min is allowed before discharging, according to the length of the 

    drain pipe, and check whether water leaks from the joints.

    

CAUTIONS: 

If there is any malfunction, please resolve it immediately.

6

HEIGHT COMpENSATION SETTING

Installation Height

Height Code

DS11

DS12

2.3-2.7(m)

H0

OFF

OFF

2.7-3.1(m)

H1

OFF

ON

3.1-3.5(m)

H2

ON

OFF

>3.5(m)

H3

ON

ON

Note

1.Please disconnect the unit from power

   supply when change these settings.

2.If you feel too noisy, please set DS11 and 

   DS12 to lower height code level.

The compensation setting according to installation height can be done by using the dip switch 11 and 12 on controller PCB.

Power supply wiring

Mainbus communication and R/C wiring

1.Unscrew and remove the electrical box cover.

2.Connect the power supply wirings to the power supply 

terminal block.

3.When doing this, press the power supply wirings 

cunder the wire clip.

1.Unscrew and remove the electrical box cover.

2.Connect R/C wirings to R1,R2 terminal block and the 

mainbus wirings to F1,F2 terminal block.

3.Press the wirings under the wire clip tightly.

NOTE: 

For how to cnnect the power wire and communication wire between outdoor unit and indoor units, please refer to chapter 9 

“Field wiring” in outdoor unit installation manual.