Pre-installation Instructions 

 

Before the Installation 

User Representative 

Schedule the installation when the User Representative will be available. One of the important 
duties of the Varian Representative is to familiarize the User Representative with the basic 
functions of the LC/MS. 

;

 

Check the checklist box: User Representative will be available during the 
installation and certification period

Entrance 

Before arranging delivery of the LC/MS, determine that there is sufficient clearance to move the 
shipping cartons to the installation site. The largest shipping carton is 72 cm (28 in.) wide by 
92 cm (36 in.) long. If the cartons are to be moved with the pallet, at least 92 cm (36 in.) 
clearance is needed. Allow additional room for maneuvering the shipping containers around 
corners and through doors. 

;

 

Check the checklist box: Entrance to the installation site is at least 92 cm 

(36 in.) wide. 

 

CAUTION

 

The MS, foreline pumps, and LC are heavy. To prevent 
personal injury, use appropriate moving and lifting 
techniques. 

Bench Space and Load  

Use the following information to plan the layout of your LC/MS system. The Varian 
Representative will unpack the cartons and put the modules on the bench.  

Figure 1 shows a possible layout for the LC/MS with the 212-LC pumps and the 460-LC 
AutoSampler. Tables 1 and 2 provide information about the bench. 

Figure 2 shows a possible layout for the LC/MS with the 212-LC pumps and the HTS PAL 
AutoSampler. Tables 3 and 4 provide information about the bench. 

The bench must be strong enough to support the weight of all modules, wide enough for all 
modules, and at least 84 cm (33 in.) deep for the MS. 

Summary of Contents for varian 320-MS LC/MS

Page 1: ...114 kg 250 lb 320 MS with HTS PAL at least 103 kg 231 lb Bench does not vibrate Exhaust system is suitable Temperature maintained between 16 and 30 C 61 86 F Relative humidity maintained between 20 a...

Page 2: ...s can be analyzed After meeting all of these requirements contact the Customer Service office in your region to schedule the installation The LC MS operates reliably under carefully controlled environ...

Page 3: ...needed Allow additional room for maneuvering the shipping containers around corners and through doors Check the checklist box Entrance to the installation site is at least 92 cm 36 in wide CAUTION The...

Page 4: ...ut the modules in Figure 1 Table 1 Bench Width with the 460 LC Bench Width 212 LC 460 LC MS CPU Monitor and Keyboard Total cm 26 30 53 5 18 7 51 178 cm in 10 5 12 21 7 5 20 71 in Table 2 Bench Load wi...

Page 5: ...5 11 5 231 lb The system requires a clean flat bench The bench must be strong enough to support the weight of the modules The area under the bench must be large enough for the foreline pump If the be...

Page 6: ...have sufficient room to connect the MS to the foreline pump If the distance between the bench and the wall is less than 10 2 4 in then the bench must be at least 94 cm 37 in deep To accommodate the v...

Page 7: ...least 20 L min to a separate vent line Ensure that the exhaust system does not pull a vacuum on the API chamber Consult local regulations for the proper method of exhausting the fumes Check the checkl...

Page 8: ...er particulate matter Particulate matter may block airflow vents causing the electronics to overheat Check the checklist box Installation site is free of excessive particulate matter Power Requirement...

Page 9: ...instruments and equipment Never plug the mass spectrometer and the chromatograph into the same power source or the power source may overload Never use the free outlet on any of the power sources for e...

Page 10: ...ags or transients The voltage must meet EN IEC 61000 4 5 and EN IEC 61000 4 11 standards for voltage stability A measured ground to neutral potential of greater than 3V ac or V dc indicates grounding...

Page 11: ...erators require regular maintenance The customer is responsible for setting up the preventive maintenance procedures and schedules contact the nitrogen generator manufacturer The Varian Warranty does...

Page 12: ...ean and new volumetric flask for optional APCI Table 14 Solvents for ESI or APCI Quantity each Solvent 2 4 liter bottle HPLC grade or better water new and unopened 2 4 liter bottle HPLC grade or bette...

Page 13: ...ansit and instrument damage may have occurred One indicator is on the exterior Read and follow the instructions on the label If the tube on the ShockWatch indicator is red the carton was dropped in tr...

Page 14: ...e and the conditions of delivery accepted The process requires at least three days Spare Parts Please refer to the Quadrupole Hardware Manual which has list of spare parts for routine operation Preven...